Heavy construction wages: Camas, Idaho

Wage determination ID20260043 · Active · Standard

Camas

Get an email when this determination changes.
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 22026-05-18diff vs rev 1
rev 12026-05-17diff vs rev 0
rev 02026-01-30original

Current rates (rev 2) · download CSV · print this page for your bid file

ClassificationRateFringeTotal
ELECTRICIAN$40.00$18.74$58.74
POWER EQUIPMENT OPERATOR: GROUP 8 BULLDOZER, SCRAPER (OVER 80 YDS TO 100 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE$37.58$16.10$53.68
POWER EQUIPMENT OPERATOR: GROUP 7: DRILL (BIT 8 IN AND OVER), HEAVY DUTY MECHANIC, SCRAPERS (OVER 40 YDS TO 60 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE$37.35$16.10$53.45
POWER EQUIPMENT OPERATOR: GROUP 6 DRILLING (BIT UNDER 8IN), SCRAPER (UP TO AND INCLUDING 40 YDS) - 60 MILES: $30.00/PER DAY Zone 3 More than 60 miles: $35.00/per day. If a project is located in more than one zone the lower zone rate shall apply ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. Trucks 100 ft to 150 ft $.15 over scale Over 200 ft $.45 over scale$36.98$16.10$53.08
POWER EQUIPMENT OPERATOR: GROUP 3 ROLLER ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE$36.33$16.10$52.43
POWER EQUIPMENT OPERATOR: GROUP 10 SCRAPER (OVER 100 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE$38.06$16.10$54.16
IRONWORKER, STRUCTURAL$33.37$22.98$56.35
LABORER: GROUP 3 ASPHALT INCLUDING RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR$33.83$16.50$50.33
LABORER: GROUP 1 FLAGGER$33.63$16.50$50.13
TRUCK DRIVER: WATER TRUCK$23.89$9.52$33.41
TRUCK DRIVER: LOWBOY TRUCK$21.00$12.10$33.10
TRUCK DRIVER: DUMP TRUCK$17.11$0.00$17.11
TREATMENT PLANTS: OPERATOR: EXCAVATOR$20.24$0.00$20.24
PAINTER: ROLLER AND SPRAY$17.90$0.00$17.90
OPERATOR: CONCRETE BATCH PLANT$24.94$11.96$36.90
OPERATOR: LOADER (FRONT END)$18.91$0.00$18.91
OPERATOR: GRADER/BLADE$25.17$9.44$34.61
OPERATOR: FORKLIFT$21.98$0.00$21.98
OPERATOR: CRANE$27.59$9.60$37.19
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$17.00$0.00$17.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$21.06$0.00$21.06
LABORER: PIPELAYER$16.39$0.00$16.39
LABORER: COMMON OR GENERAL$21.08$9.94$31.02
IRONWORKER, REINFORCING$27.22$16.70$43.92
CEMENT MASON/CONCRETE FINISHER$17.16$5.67$22.83
CARPENTER, EXCLUDES FORM WORK$28.00$0.00$28.00
CARPENTER (FORM WORK ONLY)$28.00$0.00$28.00