Heavy construction wages: Boundary, Idaho

Wage determination ID20260041 · Active · Standard

Boundary

Get an email when this determination changes.
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 12026-05-18diff vs rev 0
rev 02026-05-17original

Current rates (rev 1) · download CSV · print this page for your bid file

ClassificationRateFringeTotal
CARPENTER (FORM WORK ONLY)$38.87$17.84$56.71
ELECTRICIAN$49.55$19.09$68.64
POWER EQUIPMENT OPERATOR: GROUP 8 CRANES (85 TONS & OVER), FRONT END LOADER (10 YDS & OVER) ZONE PAY: ZONE CENTERS: SPOKANE, PASCO, LEWISTON ZONE 1: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00 OVER SCALE (B): OVER 250': $.80 OVER SCALE$30.41$15.95$46.36
POWER EQUIPMENT OPERATOR: GROUP 7 BACKHOE (OVER 110,000 GW), CRANES (45-85 TONS), HEAVY DUTY MECHANIC, FRONT END LOADER (8-10 YDS) ZONE PAY: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00 BOOM PAY (ALL CRANES): (A): 180'-250': $.50 OVER SCALE (B): OVER 250': $.80 OVER SCALE$29.31$15.95$45.26
POWER EQUIPMENT OPERATOR: GROUP 6 BACKHOE (45,000-110,000 GW), CRANE (25-45 TONS), BULLDOZER (D-6 AND OVER), GRADER/BLADE, FRONT-END LOADER(4-8 YDS), PAVER, SCRAPERS (ALL) ZONE PAY: ZONE CENTERS: SPOKANE, PASCO, LEWISTON ZONE 1: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00 BOOM PAY (ALL CRANES): (A): 180'-250': $.50 OVER SCALE (B): OVER 250': $.80 OVER SCALE$29.04$15.95$44.99
POWER EQUIPMENT OPERATOR: GROUP 5: BACKHOE (45,000 GW & UNDER), CRANES (25 TONS & UNDER), DRILL (8 IN BIT AND OVER ZONE PAY: ZONE CENTERS: SPOKANE, PASCO, LEWISTON ZONE 1: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00 BOOM PAY (ALL CRANES): (A): 180'-250': $.50 OVER SCALE (B): OVER 250': $.80 OVER SCALE$28.76$15.95$44.71
POWER EQUIPMENT OPERATOR: GROUP 4 FRONT END LOADER (UNDER 4 YDS) ZONE PAY: ZONE CENTERS: SPOKANE, PASCO, LEWISTON ZONE 1: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00 BOOM PAY (ALL CRANES): (A): 180'-250': $.50 OVER SCALE (B): OVER 250': $.80 OVER SCALE$28.60$15.95$44.55
POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER (UP TO D-6) ZONE PAY: ZONE CENTERS: SPOKANE, PASCO, LEWISTON ZONE 1: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00$28.44$15.95$44.39
POWER EQUIPMENT OPERATOR: GROUP 1 ROLLERS (ALL) ZONE PAY: ZONE CENTERS: SPOKANE, PASCO, LEWISTON ZONE 1: 0-45 MILES: FREE ZONE 2: 45 MILES & OVER: $2.00$27.51$15.95$43.46
IRONWORKER: REINFORCING AND STRUCTURAL$43.40$30.27$73.67
LABORER (PIPELINE ONLY): COMMON$26.28$12.15$38.43
LABORER:GROUP 1A FLAGGER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $2.00 BASE POINTS: SPOKANE ZONE 1: 0-45 RADIUS MILES FROM THE MAIN POST OFFICE. ZONE 2: 45 RADIUS MILES AND OVER FROM THE MAIN POST OFFICE$25.84$13.00$38.84
LABORER: GROUP 4 ASPHALT INCLUDES RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $2.00 BASE POINTS: SPOKANE ZONE 1: 0-45 RADIUS MILES FROM THE MAIN POST OFFICE. ZONE 2: 45 RADIUS MILES AND OVER FROM THE MAIN POST OFFICE$28.48$13.00$41.48
CEMENT MASON/CONCRETE FINISHER (ZONE 1) ZONE DIFFERENTIAL (ADD TO ZONE 1 RATE): ZONE 2 - $3.00 BASE POINTS: SPOKANE, PASCO, LEWISTON, WENATCHEE ZONE 1: 0-45 RADIUS MILES FROM THE MAIN POST OFFICE ZONE 2: OVER 45 RADIUS MILES FROM THE MAIN POST OFFICE$40.89$18.64$59.53
TRUCK DRIVER: WATER TRUCK$24.48$11.67$36.15
TRUCK DRIVER: LOWBOY TRUCK$21.00$12.10$33.10
OPERATOR: CONCRETE BATCH PLANT$24.94$11.96$36.90
OPERATOR: FORKLIFT$21.20$0.00$21.20
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$20.97$0.00$20.97
LABORER: PIPELAYER$17.67$7.26$24.93
LABORER: LANDSCAPE$22.13$11.13$33.26
LABORER: COMMON OR GENERAL$23.75$8.98$32.73
CARPENTER, EXCLUDES FORM WORK$29.92$5.20$35.12
TRUCK DRIVER: DUMP (OVER 6 YDS)$37.02$20.93$57.95
TRUCK DRIVER: DUMP (6 YDS AND UNDER)$36.58$20.93$57.51