| BRICKLAYER | $30.00 | $17.78 | $47.78 |
| CARPENTER ZONE PAY: ZONE 1 0-30 MILES: FREE ZONE 3 MORE THAN 60 MILES: $3.00/PER HOUR IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $35.68 | $18.24 | $53.92 |
| ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING) | $40.00 | $18.74 | $58.74 |
| POWER EQUIPMENT OPERATOR: GROUP 7 EXCAVATOR, CRANE (OVER 50 TONS), TOWER CRANE, HEAVY DUTY MECHANIC SUPPLIED AIR SHALL RECEIVE $1.00 PER HOUR ABOVE CLASSIFICATION) ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE Zone 2 30 - 60 miles: $30.00/per day Zone 3 More than 60 miles: $35.00/per day. 150ft, fifteen cents over scale B. Crane Booms, 150 ft to 200 ft, thirty cents over scale C. Crane Booms, over 200 ft., forty-five cents over scale | $37.35 | $16.10 | $53.45 |
| POWER EQUIPMENT OPERATOR: GROUP 6 BACKHOE (3/4 YD TO 3 1/2 YD), CRANE (UP TO AND INCLUDING 50 TON) POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. CRANE LONG BOOM PAY: A. CRANE BOOMS, 100FT TO 150FT, FIFTEEN CENTS OVER SCALE B. CRANE BOOMS, 150 FT TO 200 FT, THIRTY CENTS OVER SCALE C. CRANE BOOMS, OVER 200 FT., FORTY-FIVE CENTS OVER SCALE | $36.98 | $16.10 | $53.08 |
| POWER EQUIPMENT OPERATOR: GROUP 5 BACKHOE (UP TO 3/4 YD), INDUSTRIAL OILER ZONE 1 (ANYONE WORKING ON HAZMAT JOBS WORKING WITH SUPPLIED AIR SHALL RECEIVE $1.00 PER HOUR ABOVE CLASSIFICATION) ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY | $36.81 | $16.10 | $52.91 |
| POWER EQUIPMENT OPERATOR: GROUP 3 FORKLIFT ZONE 1 (ANYONE WORKING ON HAZMAT JOBS WORKING WITH SUPPLIED AIR SHALL RECEIVE $1.00 PER HOUR ABOVE CLASSIFICATION) ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY | $36.33 | $16.10 | $52.43 |
| IRONWORKER, STRUCTURAL | $33.37 | $22.98 | $56.35 |
| LABORER: GROUP 1 COMMON OR GENERAL | $32.62 | $16.50 | $49.12 |
| LABORER: GROUP 4 MASON TENDER - CEMENT/CONCRETE | $33.93 | $16.50 | $50.43 |
| LABORER: GROUP 1 COMMON OR GENERAL | $32.62 | $16.50 | $49.12 |
| LABORER: GROUP 4 MASON TENDER - CEMENT/CONCRETE | $33.93 | $16.50 | $50.43 |
| PLUMBER | $36.75 | $18.93 | $55.68 |
| ROOFER | $29.02 | $19.90 | $48.92 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT INSTALLATION | $35.50 | $22.25 | $57.75 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $26.80 | $12.00 | $38.80 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $16.12 | $0.00 | $16.12 |
| INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $20.13 | $1.80 | $21.93 |
| CEMENT MASON/CONCRETE FINISHER | $14.76 | $2.80 | $17.56 |
| TRUCK DRIVER, GROUP 5F DUMP (OVER 100 YDS) | $37.19 | $17.00 | $54.19 |
| TRUCK DRIVER, GROUP 5E DUMP (75-100 YDS) | $36.75 | $17.00 | $53.75 |
| TRUCK DRIVER, GROUP 5D DUMP (50-75 YDS) | $36.12 | $17.00 | $53.12 |
| TRUCK DRIVER, GROUP 5C DUMP (30-50 YDS) | $36.01 | $17.00 | $53.01 |
| TRUCK DRIVER, GROUP 5B DUMP (16-30 YDS) | $35.78 | $17.00 | $52.78 |
| TRUCK DRIVER, GROUP 5A DUMP (0-16 YDS) | $35.60 | $17.00 | $52.60 |