Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $48.48 | $33.91 | $82.39 |
| TILE SETTER | $30.65 | $20.10 | $50.75 |
| BRICKLAYER | $30.65 | $20.10 | $50.75 |
| ELECTRICIAN | $35.39 | $15.59 | $50.98 |
| ELEVATOR MECHANIC | $56.30 | $38.44 | $94.74 |
| POWER EQUIPMENT OPERATOR: (CLASS 3)- BOBCAT/SKID STEER/SKID LOADER, PAVER (ALL TYPES), ROLLER | $35.29 | $18.35 | $53.64 |
| POWER EQUIPMENT OPERATOR: (CLASS 2)- LOADER | $37.62 | $18.35 | $55.97 |
| POWER EQUIPMENT OPERATOR: (CLASS 1)- BACKHOE/EXCAVATOR/TRACKHOE | $39.00 | $18.35 | $57.35 |
| IRONWORKER: STRUCTURAL | $35.53 | $24.45 | $59.98 |
| IRONWORKER: ORNAMENTAL | $35.53 | $24.45 | $59.98 |
| IRONWORKER: REINFORCING | $37.50 | $30.99 | $68.49 |
| LABORER: PIPELAYER | $25.17 | $19.82 | $44.99 |
| PAINTER: BRUSH AND ROLLER | $29.55 | $12.10 | $41.65 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $45.99 | $26.42 | $72.41 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $22.57 | $9.41 | $31.98 |
| ROOFER | $21.92 | $5.07 | $26.99 |
| PLUMBER | $24.71 | $8.80 | $33.51 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION | $20.29 | $8.57 | $28.86 |
| PAINTER: SPRAY | $19.76 | $9.05 | $28.81 |
| OPERATOR: FORKLIFT | $22.96 | $7.49 | $30.45 |
| OPERATOR: CRANE | $24.15 | $8.10 | $32.25 |
| OPERATOR: BULLDOZER | $26.13 | $13.56 | $39.69 |
| LABORER: MASON TENDER - BRICK | $19.39 | $8.17 | $27.56 |
| LABORER: COMMON OR GENERAL | $14.56 | $2.47 | $17.03 |
| INSULATOR: MECHANICAL (DUCT, PIPE AND MECHANICAL SYSTEM INSULATION) | $23.28 | $8.91 | $32.19 |
| CEMENT MASON/CONCRETE FINISHER | $20.74 | $4.16 | $24.90 |
| CARPENTER | $22.13 | $7.61 | $29.74 |
| BRICKLAYER | $24.90 | $9.60 | $34.50 |