Heavy construction wages: Bryan, Effingham, Georgia
Wage determination GA20260294 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/GA20260294 on · latest revision 1 · verify at sam.gov/wage-determination/GA20260294/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: ROLLER | $11.89 | $0.00 | $11.89 |
| OPERATOR: LOADER | $22.13 | $0.00 | $22.13 |
| OPERATOR: CRANE | $25.45 | $0.00 | $25.45 |
| OPERATOR: BULLDOZER | $16.29 | $0.00 | $16.29 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $22.31 | $3.29 | $25.60 |
| LABORER: PIPELAYER | $16.95 | $0.00 | $16.95 |
| LABORER: COMMON OR GENERAL | $15.81 | $2.44 | $18.25 |
| ELECTRICIAN | $23.67 | $8.02 | $31.69 |
| CEMENT MASON/CONCRETE FINISHER | $21.40 | $4.25 | $25.65 |
| CARPENTER, EXCLUDES FORM WORK | $24.34 | $4.53 | $28.87 |
| CARPENTER (FORM WORK ONLY) | $24.02 | $10.71 | $34.73 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.