Heavy construction wages: Banks, Habersham, Georgia
Wage determination GA20260062 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/GA20260062 on July 24, 2026 · latest revision 1 · verify at sam.gov/wage-determination/GA20260062/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: DUMP TRUCK | $16.41 | $2.93 | $19.34 |
| OPERATOR: LOADER | $21.77 | $0.00 | $21.77 |
| OPERATOR: GRADER/BLADE | $25.82 | $1.81 | $27.63 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $24.89 | $0.00 | $24.89 |
| LABORER: PIPELAYER | $16.08 | $0.00 | $16.08 |
| LABORER: COMMON OR GENERAL | $16.07 | $0.00 | $16.07 |
| ELECTRICIAN | $28.40 | $0.52 | $28.92 |
| CEMENT MASON/CONCRETE FINISHER | $19.30 | $2.43 | $21.73 |
| CARPENTER (FORM WORK ONLY) | $20.51 | $0.01 | $20.52 |