2 rate changes, 6 added, 4 removed.

Rate changes

Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.

ClassificationOld totalNew totalΔ/hrHours on jobCost impact
TRAFFIC SIGNALIZATION: TRAFFIC SIGNAL INSTALLATION ZONE 1 (SUMMIT COUNTY) TRAFFIC SIGNAL INSTALLER ZONE DEFINITIONS ZONE 1 SHALL BE A 35 MILE RADIUS, MEASURED FROM THE FOLLOWING ADDRESSES IN EACH OF THE FOLLOWING CITIES: COLORADO SPRINGS - NEVADA & BIJOU DENVER - ELLSWORTH AVENUE & BROADWAY FT. COLLINS - PROSPECT & COLLEGE GRAND JUNCTION - 12TH & NORTH AVENUE PUEBLO - I-25 & HIGHWAY 50 ALL WORK OUTSIDE OF THESE AREAS SHALL BE PAID ZONE 2 RATES$35.10$36.35+1.25
TRAFFIC SIGNALIZATION: TRAFFIC SIGNAL INSTALLATION ZONE 2 (SUMMIT COUNTY) TRAFFIC SIGNAL INSTALLER ZONE DEFINITIONS ZONE 1 SHALL BE A 35 MILE RADIUS, MEASURED FROM THE FOLLOWING ADDRESSES IN EACH OF THE FOLLOWING CITIES: COLORADO SPRINGS - NEVADA & BIJOU DENVER - ELLSWORTH AVENUE & BROADWAY FT. COLLINS - PROSPECT & COLLEGE GRAND JUNCTION - 12TH & NORTH AVENUE PUEBLO - I-25 & HIGHWAY 50 ALL WORK OUTSIDE OF THESE AREAS SHALL BE PAID ZONE 2 RATES$38.10$39.50+1.40

Added classifications

POWER EQUIPMENT OPERATOR: ROLLER/COMPACTOR (DIRT AND GRADE COMPACTION) (RIO BLANCO)$23.67$9.22
POWER EQUIPMENT OPERATOR: LOADER (FRONT END) (RIO BLANCO)$23.67$9.22
POWER EQUIPMENT OPERATOR: LOADER (FRONT END) (GRAND, PITKIN)$22.67$8.72
POWER EQUIPMENT OPERATOR: BROOM/SWEEPER (SUMMIT)$22.67$8.72
POWER EQUIPMENT OPERATOR: ASPHALT ROLLER (GRAND)$22.67$8.72
POWER EQUIPMENT OPERATOR: ASPHALT LAYDOWN (RIO BLANCO)$23.67$9.22

Removed classifications

POWER EQUIPMENT OPERATOR - Rio Blancowas $23.67
POWER EQUIPMENT OPERATOR - Grandwas $22.67
POWER EQUIPMENT OPERATOR - Summitwas $22.67
POWER EQUIPMENT OPERATOR - Grand, Pitkinwas $22.67