CA20260018: rev 5 → rev 6

6 rate change(s), 143 added, 154 removed.

Rate changes

Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.

ClassificationOld totalNew totalΔ/hrHours on jobCost impact
IRONWORKERS: ORNAMENTAL, REINFORCING AND STRUCTURAL (ALAMEDA, CONTRA COSTA, SAN MATEO, SANTA CLARA COUNTIES) PREMIUM PAY: $6.00 ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: CHINA LAKE NAVAL TEST STATION, CHOCOLATE MOUNTAINS NAVAL RESERVE-NILAND, EDWARDS AFB, FORT IRWIN MILITARY STATION, FORT IRWIN TRAINING CENTER-GOLDSTONE, SAN CLEMENTE ISLAND, SAN NICHOLAS ISLAND, SUSANVILLE FEDERAL PRISON, 29 PALMS-MARINE CORPS, U.S. MARINE BASE-BARSTOW, U.S. NAVAL AIR FACILITY-SEALY, VENDENBERG AFB$90.48$4.00-86.48
IRONWORKERS: FENCE ERECTOR (ALAMEDA, CONTRA COSTA, SAN MATEO, SANTA CLARA COUNTIES). PREMIUM PAY: $6.00 ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: CHINA LAKE NAVAL TEST STATION, CHOCOLATE MOUNTAINS NAVAL RESERVE-NILAND, EDWARDS AFB, FORT IRWIN MILITARY STATION, FORT IRWIN TRAINING CENTER-GOLDSTONE, SAN CLEMENTE ISLAND, SAN NICHOLAS ISLAND, SUSANVILLE FEDERAL PRISON, 29 PALMS-MARINE CORPS, U.S. MARINE BASE-BARSTOW, U.S. NAVAL AIR FACILITY-SEALY, VENDENBERG AFB$72.29$4.00-68.29
IRONWORKERS: ORNAMENTAL, REINFORCING AND STRUCTURAL (SAN FRANCISCO CITY AND COUNTY) PREMIUM PAY: $6.00 ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: CHINA LAKE NAVAL TEST STATION, CHOCOLATE MOUNTAINS NAVAL RESERVE-NILAND, EDWARDS AFB, FORT IRWIN MILITARY STATION, FORT IRWIN TRAINING CENTER-GOLDSTONE, SAN CLEMENTE ISLAND, SAN NICHOLAS ISLAND, SUSANVILLE FEDERAL PRISON, 29 PALMS-MARINE CORPS, U.S. MARINE BASE-BARSTOW, U.S. NAVAL AIR FACILITY-SEALY, VENDENBERG AFB$90.98$4.00-86.98
IRONWORKERS: FENCE ERECTOR (SAN FRANCISCO CITY AND COUNTY) PREMIUM PAY: $6.00 ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: CHINA LAKE NAVAL TEST STATION, CHOCOLATE MOUNTAINS NAVAL RESERVE-NILAND, EDWARDS AFB, FORT IRWIN MILITARY STATION, FORT IRWIN TRAINING CENTER-GOLDSTONE, SAN CLEMENTE ISLAND, SAN NICHOLAS ISLAND, SUSANVILLE FEDERAL PRISON, 29 PALMS-MARINE CORPS, U.S. MARINE BASE-BARSTOW, U.S. NAVAL AIR FACILITY-SEALY, VENDENBERG AFB$72.29$4.00-68.29
IRONWORKER: ORNAMENTAL, REINFORCING AND STRUCTURAL (REMAINING COUNTIES) PREMIUM PAY: $6.00 ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: CHINA LAKE NAVAL TEST STATION, CHOCOLATE MOUNTAINS NAVAL RESERVE-NILAND, EDWARDS AFB, FORT IRWIN MILITARY STATION, FORT IRWIN TRAINING CENTER-GOLDSTONE, SAN CLEMENTE ISLAND, SAN NICHOLAS ISLAND, SUSANVILLE FEDERAL PRISON, 29 PALMS-MARINE CORPS, U.S. MARINE BASE-BARSTOW, U.S. NAVAL AIR FACILITY-SEALY, VENDENBERG AFB$85.85$4.00-81.85
IRONWORKER: FENCE ERECTOR (REMAINING COUNTIES) PREMIUM PAY: $6.00 ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: CHINA LAKE NAVAL TEST STATION, CHOCOLATE MOUNTAINS NAVAL RESERVE-NILAND, EDWARDS AFB, FORT IRWIN MILITARY STATION, FORT IRWIN TRAINING CENTER-GOLDSTONE, SAN CLEMENTE ISLAND, SAN NICHOLAS ISLAND, SUSANVILLE FEDERAL PRISON, 29 PALMS-MARINE CORPS, U.S. MARINE BASE-BARSTOW, U.S. NAVAL AIR FACILITY-SEALY, VENDENBERG AFB$72.29$4.00-68.29

Added classifications

ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER: INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT (AREA 1: CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED, MONTEREY, SAN BENITO, SAN JOAQUIN, SANTA CRUZ, STANISLAUS, & TOULMNE COUNTIES)$34.56$11.40
DIVER: DIVER TENDER. DEPTH PAY (SURFACE DIVING): 50 TO 100 FT, $2.00 PER FOOT; 101 TO 150 FT, $3.00 PER FOOT; 151 TO 220 FT, $4.00 PER FOOT; 221 FT. AND DEEPER, $5.00 PER FOOT. (SATURATION DIVING: THE STANDBY RATE SHALL APPLY UNTIL SATURATION STARTS. THE SATURATION DIVING RATE APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS.) (DIVING IN ENCLOSURES: WHERE IT IS NECESSARY FOR DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT. WHEN IT IS NECESSARY FOR A DIVER TO ENTER ANY PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48" IN HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT.) (WORK IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT.)$59.51$34.69
DIVER: MANIFOLD OPERATOR (STANDBY). DEPTH PAY (SURFACE DIVING): 50 TO 100 FT, $2.00 PER FOOT; 101 TO 150 FT, $3.00 PER FOOT; 151 TO 220 FT, $4.00 PER FOOT; 221 FT. AND DEEPER, $5.00 PER FOOT. (SATURATION DIVING: THE STANDBY RATE SHALL APPLY UNTIL SATURATION STARTS. THE SATURATION DIVING RATE APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS.) (DIVING IN ENCLOSURES: WHERE IT IS NECESSARY FOR DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT. WHEN IT IS NECESSARY FOR A DIVER TO ENTER ANY PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48" IN HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT.) (WORK IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFT.)$59.51$34.69
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 2 (LIFTING DEVICES)- DERRICK BARGE PEDESTAL MOUNTED 45 TONS TO AND INCLUDING 100 TONS; CLAMSHELL UP TO AND INCLUDING 7 CU. YDS.; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 45 TONS; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED, OVER 45 TONS UP TO AND INCLUDING 100 TONS; FUNDEX F-12 HYDRAULIC PILE RIG$50.82$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 2 (OILER)- DERRICK BARGE PEDESTAL MOUNTED 45 TONS TO AND INCLUDING 100 TONS; CLAMSHELL UP TO AND INCLUDING 7 CU. YDS.; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 45 TONS; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED, OVER 45 TONS UP TO AND INCLUDING 100 TONS; FUNDEX F-12 HYDRAULIC PILE RIG$43.11$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 1 (LIFTING DEVICES)- DERRICK BARGE PEDESTAL MOUNTED OVER 100 TONS; CLAMSHELL OVER 7 CU. YDS.; SELF-PROPELLED BOOM-TYHPE LIFTING DEVICE OVER 100 TONS; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED OVER 100 TONS$52.64$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 1 (OILER)- DERRICK BARGE PEDESTAL MOUNTED OVER 100 TONS; CLAMSHELL OVER 7 CU. YDS.; SELF-PROPELLED BOOM-TYHPE LIFTING DEVICE OVER 100 TONS; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED OVER 100 TONS$43.38$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 1 (TRUCK CRANE OILER)- DERRICK BARGE PEDESTAL MOUNTED OVER 100 TONS; CLAMSHELL OVER 7 CU. YDS.; SELF-PROPELLED BOOM-TYHPE LIFTING DEVICE OVER 100 TONS; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED OVER 100 TONS$45.66$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 2 (TRUCK CRANE OILER)- DERRICK BARGE PEDESTAL MOUNTED 45 TONS TO AND INCLUDING 100 TONS; CLAMSHELL UP TO AND INCLUDING 7 CU. YDS.; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 45 TONS; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED, OVER 45 TONS UP TO AND INCLUDING 100 TONS; FUNDEX F-12 HYDRAULIC PILE RIG$45.41$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 3 (LIFTING DEVICES)- DERRICK BARGE PEDESTAL MOUNTED UNDER 45 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER; SKID/SCOW PILEDRIVER, ANY TONNAGE; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED 45 TONS AND UNDER$49.14$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 3 (OILER)- DERRICK BARGE PEDESTAL MOUNTED UNDER 45 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER; SKID/SCOW PILEDRIVER, ANY TONNAGE; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED 45 TONS AND UNDER$42.89$31.15
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 8- BIT SHARPENER; BOILER TENDER; BOX OPERATOR; BRAKEPERSON; COMBINATION MIXER AND COMPRESSOR (SHOTCRETE/GUNITE); COMPRESSOR OPERATOR; DECKHAND; FIRE TENDER; FORKLIFT (UNDER 20 FT); GENERATOR; GUNITE/SHOTCRETE EQUIPMENT OPERATOR; HYDRAULIC MONITOR; KEN SEAL MACHINE (OR SIMILAR); MIXERMOBILE; OILER; PUMPOPERATOR; REFRIGERATOR PLANT; RESERVOIR-DEBRIS TUG (SELF-PROPELLED FLOATING); ROSS CARRIER (CONSTRUCTION SITE); ROTOMIST OPERATOR; SELF-PROPELLED TAPE MACHINE; SHUTTLECAR; SELF-PROPELLED POWER SWEEPER OPERATOR (INCLUDES VACUUM SWEEPER); SLUSHER OPERATOR; SURFACE HEATER; SWITCHPERSON; TAR POT FIRETENDER; TUGGER HOIST, SINGLE DRUM; VACUUM COOLING PLANT; WELDING MACHINE (POWERED OTHER THAN BY ELECTRICITY. ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$57.70$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 8-A - ELEVATOR OPERATOR; SKIDSTEER LOADER-BOBCAT 743 SERIES OR SMALLER, AND SIMILAR (WITHOUT ATTACHMENTS); MINI EXCAVATOR UNDER 25 H.P. (BACKHOE-TRENCHER); TUB GRINDER WOOD CHIPPER. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$55.49$32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 1 (CRANES)- CRANE OVER 100 TONS; DERRICK OVER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 100 TONS$68.81$32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 1 (OILER)- CRANE OVER 100 TONS; DERRICK OVER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 100 TONS$43.72$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 1 (TRUCK CRANE OILER)- CRANE OVER 100 TONS; DERRICK OVER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 100 TONS$45.95$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 2 (CRANES)- CRANE OVER 45 TONS TO 100 TONS; DERRICK UNDER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 45 TONS TO 100 TONS; TOWER CRANE$67.04$32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 2 (OILER)- CRANE OVER 45 TONS TO 100 TONS; DERRICK UNDER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 45 TONS TO 100 TONS; TOWER CRANE$43.45$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 2 (TRUCK CRANE OILER)- CRANE OVER 45 TONS TO 100 TONS; DERRICK UNDER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE OVER 45 TONS TO 100 TONS; TOWER CRANE$45.73$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 3 (CRANES)- CRANE, 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, 45 TONS AND UNDER$65.56$32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 3 (HYDRAULIC)- CRANE, 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, 45 TONS AND UNDER$45.07$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 3 (OILER)- CRANE, 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, 45 TONS AND UNDER$43.23$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 3 (TRUCK CRANE OILER)- CRANE, 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, 45 TONS AND UNDER$45.46$31.15
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 4 (CRANES)- CHICAGO BOOM; FORKLIFT, 10 TONS AND OVER; HEAVY-DUTY REPAIR PERSON/WELDER$63.54$32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 5 (CRANES)- BOOM CAT$62.24$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- SHAFTS, STOPES, RAISES: AREA 1, GROUP 1- HEADING SHIELD OPERATOR; HEAVY-DUTY REPAIRPERSON; MUCKING MACHINE (RUBBER TIRED, RAIL OR TRACK TYPE); RAISED BORE OPERATOR (TUNNELS); TUNNEL MOLE BORE OPERATOR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$63.06$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- SHAFTS, STOPES, RAISES: AREA 1, GROUP 1-A- TUNNEL BORE MACHINE OPERATOR 20' DIAMETER OR MORE. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$65.53$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- SHAFTS, STOPES, RAISES: AREA 1, GROUP 2- COMBINATION SLUSHER AND MOTOR OPERATOR; CONCRETE PUMP OR PUMPCRETE GUN; POWER JUMBO OPERATOR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$61.80$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- SHAFTS, STOPES, RAISES: AREA 1, GROUP 5- BIT SHARPENER; BRAKEMAN; COMBINATION MIXER AND COMPRESSOR (GUNITE); COMPRESSOR OPERATOR; OILER; PUMP OPERATOR; SLUSHER OPERATOR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$58.19$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- UNDERGOUND: AREA 1, GROUP 1- HEADING SHIELD OPERATOR; HEAVY-DUTY REPAIRPERSON; MUCKING MACHINE (RUBBER TIRED, RAIL OR TRACK TYPE); RAISED BORE OPERATOR (TUNNELS); TUNNEL MOLE BORE OPERATOR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$62.96$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- UNDERGOUND: AREA 1, GROUP 1-A- TUNNEL BORE MACHINE OPERATOR 20' DIAMETER OR MORE. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$65.43$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- UNDERGOUND: AREA 1, GROUP 2- COMBINATION SLUSHER AND MOTOR OPERATOR; CONCRETE PUMP OR PUMPCRETE GUN; POWER JUMBO OPERATOR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$61.70$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- UNDERGOUND: AREA 1, GROUP 3- DRILL DOCTOR; MINE OR SHAFT HOIST. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$60.37$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- UNDERGOUND: AREA 1, GROUP 4- COMBINATION SLURRY MIXER CLEANER; GROUTING MACHINE OPERATOR; MOTORMAN. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$59.23$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- UNDERGOUND: AREA 1, GROUP 5- BIT SHARPENER; BRAKEMAN; COMBINATION MIXER AND COMPRESSOR (GUNITE); COMPRESSOR OPERATOR; OILER; PUMP OPERATOR; SLUSHER OPERATOR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$58.09$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 1- OPERATOR OF HELICOPTER (WHEN USED IN ERECTION WORK); HYDRAULIC EXCAVATOR, 7 CU. YDS. AND OVER; POWER SHOVELS, OVER 7 CU. YDS. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$66.96$32.53
PER HOUR AT THE FOLLOWING LOCATIONS: ARMY DEENSE LANGUAGE INSTITUTE-MONTEREY, FALLON AIR BASE, NAVAL POST GRADUATE SCHOOL-MONTEREY, YERMO MARINE CORPS LOGISTICS CENTER$2.00
FOLLOWING LOCATIONS: PORT HUENEME, PORT MUGU, U.S. COAST GUARD STATION-TWO ROCK$45.78$26.51
FOLLOWING LOCATIONS: ARMY DEENSE LANGUAGE INSTITUTE-MONTEREY, FALLON AIR BASE, NAVAL POST GRADUATE SCHOOL-MONTEREY, YERMO MARINE CORPS LOGISTICS CENTER$2.00
FOLLOWING LOCATIONS: PORT HUENEME, PORT MUGU, U.S. COAST GUARD STATION-TWO ROCK$55.33$35.15
FOLLOWING LOCATIONS: ARMY DEENSE LANGUAGE INSTITUTE-MONTEREY, FALLON AIR BASE, NAVAL POST GRADUATE SCHOOL-MONTEREY, YERMO MARINE CORPS LOGISTICS CENTER$2.00
FOLLOWING LOCATIONS: PORT HUENEME, PORT MUGU, U.S. COAST GUARD STATION-TWO ROCK$45.78$26.51
PER HOUR AT THE FOLLOWING LOCATIONS: ARMY DEENSE LANGUAGE INSTITUTE-MONTEREY, FALLON AIR BASE, NAVAL POST GRADUATE SCHOOL-MONTEREY, YERMO MARINE CORPS LOGISTICS CENTER$2.00
FOLLOWING LOCATIONS: PORT HUENEME, PORT MUGU, U.S. COAST GUARD STATION-TWO ROCK$55.83$35.15
ADDITIONAL PER HOUR AT THE FOLLOWING LOCATIONS: ARMY DEENSE LANGUAGE INSTITUTE-MONTEREY, FALLON AIR BASE, NAVAL POST GRADUATE SCHOOL-MONTEREY, YERMO MARINE CORPS LOGISTICS CENTER$2.00
HOUR AT THE FOLLOWING LOCATIONS: PORT HUENEME, PORT MUGU, U.S. COAST GUARD STATION-TWO ROCK$45.78$26.51
FOLLOWING LOCATIONS: ARMY DEENSE LANGUAGE INSTITUTE-MONTEREY, FALLON AIR BASE, NAVAL POST GRADUATE SCHOOL-MONTEREY, YERMO MARINE CORPS LOGISTICS CENTER$2.00
FOLLOWING LOCATIONS: PORT HUENEME, PORT MUGU, U.S. COAST GUARD STATION-TWO ROCK$50.70$35.15
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$31.59$29.89
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$31.59$29.89
LABORER (CONSTRUCTION CRAFT LABORERS) GROUP 1-F- WIRE WINDING MACHINE IN CONNECTION WITH GUNITING OR SHOT CRETE.$31.37$23.20
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$36.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$36.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$36.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$29.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$36.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$36.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$36.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$36.25$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$29.94$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$29.94$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$35.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$35.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$35.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$28.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$35.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$35.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$35.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$35.25$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$28.94$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$36.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$36.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$36.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$29.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$36.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$36.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$36.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$36.25$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$29.94$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$35.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$35.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$35.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$28.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$35.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$35.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$35.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$35.25$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$28.94$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$36.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$36.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$36.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$29.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$36.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$36.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$36.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$36.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$36.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$36.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$36.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$29.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$36.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$36.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$36.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$36.25$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$29.94$27.30
PLASTER TENDER. WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. (ALAMEDA AND CONTRA COSTA COUNTIES)$41.93$30.32
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER.$35.50$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 2- ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES.$35.35$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 3- CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY).$35.25$27.30
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4- FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION".$28.94$27.30
LABORER, GUNITE: GROUP 4- GUINTE LABORER.$35.25$27.30
LABORER, WRECKING: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS, AND MATERIALS).$35.50$27.30
LABORER, WRECKING: GROUP 2- SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS).$35.35$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (1) New Construction.$35.25$27.30
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - (2) Establishment Warranty Period.$28.94$27.30
LABORER, PLASTER TENDER. WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. (CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED, SAN JOAQUIN, STANISLAUS, & TUOLUMNE COUNTIES)$39.77$28.54
SHEET METAL WORKER (MONTEREY & SAN BENITO COUNTIES)$58.52$38.67
SHEET METAL WORKER (SANTA CRUZ COUNTY)$55.16$34.18
SHEET METAL WORKER: ALL OTHER WORK (ALAMEDA, CONTRA COSTA, SAN FRANSICO, SAN MATEO, SANTA CLARA COUNTIES))$64.06$46.83
SHEET METAL WORKER: MECHANICAL CONTRACTS UNDER $200,000 (ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO, SANTA CLARA COUNTIES))$55.92$45.29
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 3 (TRUCK CRANE OILER)- DERRICK BARGE PEDESTAL MOUNTED UNDER 45 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER; SKID/SCOW PILEDRIVER, ANY TONNAGE; TRUCK CRANE OR CRAWLER, LAND OR BARGE MOUNTED 45 TONS AND UNDER$45.12$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 4 (LIFTING DEVICES)- ASSISTANT OPERATOR IN LIEU OF ASSISTANT TO ENGINEER; FORKLIFT, 10 TONS AND OVER; HEAVY-DUTY REPAIR PERSON/WELDER$47.37$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 5 (LIFTING DEVICES)- DECK ENGINEER$44.73$31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING: GROUP 6 (LIFTING DEVICES)- DECKHAND; FIRE TENDER$42.50$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 1 (CRANES)- CLAMSHELL AND DRAGLINE OVER 7 CU. YDS.; CRANE, OVER 100 TONS; DERRICK, OVER 100 TONS; DERRICK BARGE PEDESTAL-MOUNTED, OVER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, OVER 100 TONS. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$68.59$32.53
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 1 (OILER)- CLAMSHELL AND DRAGLINE OVER 7 CU. YDS.; CRANE, OVER 100 TONS; DERRICK, OVER 100 TONS; DERRICK BARGE PEDESTAL-MOUNTED, OVER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, OVER 100 TONS. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$43.79$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 1 (TRUCK CRANE OILER)- CLAMSHELL AND DRAGLINE OVER 7 CU. YDS.; CRANE, OVER 100 TONS; DERRICK, OVER 100 TONS; DERRICK BARGE PEDESTAL-MOUNTED, OVER 100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, OVER 100 TONS. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$46.08$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 2 (CRANES)- CLAMSHELL AND DRAGLINE OVER 1 CU. YD. UP TO AND INCLUDING 7 CU. YDS.; CRANE, OVER 45 TONS UP TO AND INCLUDING 100 TONS; DERRICK BARGE, 100 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, OVER 45 TONS; TOWER CRANE. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$66.08$32.53
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 2 (OILER)- CLAMSHELL AND DRAGLINE OVER 1 CU. YD. UP TO AND INCLUDING 7 CU. YDS.; CRANE, OVER 45 TONS UP TO AND INCLUDING 100 TONS; DERRICK BARGE, 100 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, OVER 45 TONS; TOWER CRANE. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$42.83$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 2 (TRUCK CRANE OILER)- CLAMSHELL AND DRAGLINE OVER 1 CU. YD. UP TO AND INCLUDING 7 CU. YDS.; CRANE, OVER 45 TONS UP TO AND INCLUDING 100 TONS; DERRICK BARGE, 100 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE, OVER 45 TONS; TOWER CRANE. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$45.07$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 3 (CRANES) CLAMSHELL AND DRAGLINE UP TO AND INCLUDING 1 CU. YD.; CRANES 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$64.34$32.53
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 3 (HYDRAULIC) CLAMSHELL AND DRAGLINE UP TO AND INCLUDING 1 CU. YD.; CRANES 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$59.98$32.53
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 3 (OILER) CLAMSHELL AND DRAGLINE UP TO AND INCLUDING 1 CU. YD.; CRANES 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$42.55$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 3 (TRUCK CRANE OILER) CLAMSHELL AND DRAGLINE UP TO AND INCLUDING 1 CU. YD.; CRANES 45 TONS AND UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45 TONS AND UNDER. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$44.83$31.15
OPERATOR: POWER EQUIPMENT- CRANES AND ATTACHMENTS - AREA 1: GROUP 4 (CRANES)- BOOM TRUCK OR DUAL PURPOSE A-FRAME TRUCK, NON-ROTATING OVER 15 TONS; TRUCK-MOUNTED ROTATING TELESCOPIC BOOM TYPE LIFTING DEVICE, MANITEX OR SIMILAR (BOOM TRUCK) OVER 15 TONS. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$61.30$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 2- HIGHLINE CABLEWAY; HYDRAULIC EXCAVATOR, 3.5 CU. YDS. UP TO 7 CU. YDS.; LICENSED CONSTRUCTION WORK BOAT OPERATOR, ON SITE; POWER BLADE OPERATOR (FINISH); POWER SHOVELS, OVER 1 CU. YD. UP TO AN DINCLUDING 7 CU. YDS. M.R.C. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$65.43$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 3- ASPHALT MILLING MACHINE; CABLE BACKHOE; COMBINATION BACKHOE AND LOADER OVER 3/4 CU. YDS.; CONTINUOUS FLIGHT TIE BACK MACHINE ASSISTNAT TO ENGINEER OR MECHANIC; CRANE MOUNTED CONTINUOUS FLIGHT TIE BACK MACHINE, TONNAGE TO APPLY; CRANE MOUNTED DRILL ATTACHMENT, TONNAGE TO APPLY; DOZER, SLOPE BRD; GRADALL; HYDRAULIC EXCAVATOR, UP TO 3.5 CU. YDS.; LOADER 4 CU. YDS. AND OVER; LONG REACH EXCAVATOR; MULTIPLE ENGINE SCRAPER (WHEN USED AS PUSH PULL); POWER SHOVELS, UP TO AND INCLUDING 1 CU. YD.; PRE-STRESS WIRE WRAPPING MACHINE; SIDE BOOM CAT, 572 OR LARGER; TRACK LOADER 4 CU. YDS. AND OVER; WHEEL EXCAVATOR (UP TO AND INCLUDING 750 CU. YDS. PER HOUR) (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$63.95$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- SHAFTS, STOPES, RAISES: AREA 1, GROUP 3- DRILL DOCTOR; MINE OR SHAFT HOIST. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$60.47$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 4- ASPHALT PLANT ENGINEER/BOX PERSON; CHICAGO BOOM; COMBINATION BACKHOE AND LOADER UP TO AND INCLUDING .75 CU. YD.; CONCRETE BATCH PLANT (WET OR DRY); DOZER AND/OR PUSH CAT; PULL-TYPE ELEVATING LOADER; GRADESETTER, GRADE CHECKER (GPS, MECHANICAL OR OTHERWISE); GROOVING AND GRINDING MACHINE; HEADING SHIELD OPERATOR; HEAVY-DUTY DRILLING EQUIPMENT, HUGHS, LDH, WATSON 3000 OR SIMILAR; HEAVY-DUTY REPAIRPERSON AND/OR WELDER; LIME SPREADER; LOADER UNDER 4 CU. YDS.; LUBRICATION AND SERVICE ENGINEER (MOBILE AND GREASE RACK); MECHANICAL FINISHERS OR SPREADER MACHINE (ASPHALT, BARBER-GREENE AND SIMILAR); MILLER FORMLESS M-9000 SLOPE PAVER OR SIMILAR; PORTABLE CRUSHING AND SCREENING PLANTS; POWER BLADE SUPPORT; ROLLER OPERATOR, ASPHALT; RUBBER-TIRED SCRAPER, SELF-LOADING (PADDLE-WHEELS, ETC.); RUBBER-TIRED EARTHMOVING EQUIPMENT (SCRAPERS); SLIP FORM PAVER (CONCRETE); SMALL TRACTOR WITH DRAG; SOIL STABILIZER (P&H OR EQUAL); SPIDER PLOW AND SPIDER PULLER; TUBEX PILE RIG; UNLICENSED CONSTRUCTION WORK BOAT OPERATOR, ON SITE; TIMBER SKIDDER; TRACK LOADER UP TO 4 YDS.; TRACTOR-DRAWN SCRAPER; TRACTOR, COMPRESSOR DRILL COMBINATION; WELDER; WOODS-MIXER (AND OTHER SIMILAR PUGMILL EQUIPMENT. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$62.57$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 5- CAST-IN-PLACE PIPE LAYING MACHINE; COMBINATION SLUSHER AND MOTOR OPERATOR; CONCRETE CONVEYOR OR CONCRETE PUMP, TRUCK OR EQUIPMENT MOUNTED; CONCRETE CONVEYOR, BUILDING SITE; CONCRETE PUMP OR PUMPCRETE GUN; DRILLING EQUIPMENT, WATSON 2000, TEXOMA 700 OR SIMILAR; DRILLING AND BORING MACHINERY, HORIZONTAL (NOT TO APPLY TO WATERLINES, WAGON DRILLS, OR JACKHAMMERS); CONCRETE MIXER/ALL; PERSON AND/OR MATERIAL HOIST; MECHANICAL FINISHERS (CONCRETE (CLARY, JOHNSON, BIDWELL BRIDGE DECK, OR SIMILAR TYPES); MECHANICAL BURM, CURB, AND/OR CURB AND GUTTER MACHINE, CONCRETE OR ASPHALT); MINE OR SHAFT HOIST; PORTABLE CRUSHER; POWER JUMBO OPERATOR (SETTING SLIP-FORMS, ETC., IN TUNNELS); SCREED (AUTOMATIC OR MANUAL); SELF-PROPELLED COMPACTOR WITH DOZER; TRACTOR WITH BOOM D6 OR SMALLER; TRENCHING MACHINE, MAXIMUM DIGGING CAPACITY OVER 5 FT. DEPTH; VERMEER T-600B ROCK CUTTER OR SIMILAR. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$61.30$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 6- ARMOR-COATER (OR SIMILAR); BALLAST JACK TAMPER; BOOM-TYPE BACKFILLING MACHINE; ASSISTANT PLANT ENGINEER; BRIDGE AND/OR GANTRY CRANE; CHEMICAL GROUTING MACHINE, TRUCK-MOUNTED; CHIP SPREADING MACHINE OPERATOR; CONCRETE SAW (SELF-PROPELLED UNIT ON STREETS, HIGHWAYS, AIRPORTS, AND CANALS); DECK ENGINEER; DRILLING EQUIPMENT TEXOMA 600, HUGHS 200 SERIES OR SIMILAR UP TO AND INCLUDING 30 FT. M.R.C.; DRILL DOCTOR; HELICOPTER RADIO OPERATOR; HYDRO-HAMMER OR SIMILAR; LINE MASTER; SKIDSTEER LOADER, BOBCAT LARGER THAN 743 SERIES OR SIMILAR (WITH ATTACHMENTS); LOCOMOTIVE; LULL HI-LIFT OR SIMILAR; OILER, TRUCK MOUNTED; PAVEMENT BREAKER, TRUCK-MOUNTED, WITH COMPRESSOR COMBINATION; PAVING FABRIC INSTALLATION AND/OR LAYING MACHINE; PIPE BENDING MACHINE (PIPELINES ONLY); PIPE WRAPPING MACHINE (TRACTOR PRPELLED AND SUPPORTED); SCREED (EXCEPT ASPHALTIC CONCRETE PAVING); SELF-PROPELLED PIPELINE WRAPPING MACHINE; TRACTOR; SELF-LOADING CHIPPER; CONCRETE BARRIER MOVING MACHINE. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$59.98$32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 7- BALLAST REGULATOR; BOOM TRUCK OR DUAL-PURPOSE A-FRAME TRUCK, NON-ROTATING-UNDER 15 TONS; CARY IFT OR SIMILAR; COMBINATION SLURRY MIER AND/OR CLEANER; DRILLING EQUIPMENT, 20 FT AND UNDER M.R.C.; FIRETENDER (HOT PLANT); GROUTING MACHINE OPERATOR; HIGHLINE CABLEWAY SIGNALPERSON; STATIONARY BELT LOADER (KOLMAN OR SIMILAR); LIFT SLAB MACHINE (VAGTBORG AND SIMILAR TYPES); MAGINNES INTERNAL FULL SLAB VIBRATOR; MATERIAL HOIST (1 DRUM); MECHANICAL TRENCH SHIELD; PAVEMENT BREAKER WITH OR WITHOUT COMPRESSOR COMBINATION); PIPE CLEANING MACHINE (TRACTOR PROPELLED AND SUPPORTED); POST DRIVER; ROLLER (EXCEPT ASPHALT); CHIP SEAL; SELF-PROPELLED AUTOMATICALLY APPLIED CONCRETE CURING MACHINE (ON STREETS, HIGHWAYS, AIRPORTS, AND CANALS); SELF-PROPELLED COMPACTOR (WITHOUT DOZER); SIGNALPERSON; SLIP-FORM PUMPS (LIFTING DEVICE FOR CONCRETE FORMS); TIE SPACE; TOWER MOBILE; TRENCHING MACHINE, MAXIMUM DIGGING CAPACITY UP TO AND INCLUDING 5 FT. DEPTH; TRUCK-TYPE LOADER. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$58.84$32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK- SHAFTS, STOPES, RAISES: AREA 1, GROUP 4- COMBINATION SLURRY MIXER CLEANER; GROUTING MACHINE OPERATOR; MOTORMAN. (AREA 1: LISTED WAGE RATES. AREA 2: RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.) (AREA 1: ALAMEDA, CALAVERAS (EXCEPT EASTERN PART), CONTRA COSTA, FRESNO (EXCEPT EASTERN PART), KINGS, MADERA (EXCEPT EASTERN PART), MARIPOSA (EXCEPT EASTERN PART), MERCED, MONTEREY (EXCEPT SOUTHWESTERN PART), SAN BENITO, SAN FANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ, STANISLAUS, TUOLUMNE (EXCEPT EASTERN PART) COUNTIES. AREA 2: CALAVERAS (EASTERN PART), FRESNO (EASTERN PART), MADERA (EASTERN PART), MARIPOSA (EASTERN PART), MONTEREY (SOUTHWESTERN PART), TUOLUMNE (EASTERN PART) COUNTIES)$59.33$32.53

Removed classifications

DIVER: MANIFOLD OPERATOR (STANDBY) DEPTH PAY (SURFACE DIVING): 050 TO 100 FT $2.00 PER FOOT 101 TO 150 FT $3.00 PER FOOT 151 TO 220 FT $4.00 PER FOOT 221 FT.-DEEPER $5.00 PER FOOT SATURATION DIVING: THE STANDBY RATE SHALL APPLY UNTIL SATURATION STARTS. THE SATURATION DIVING RATE APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS. DIVING IN ENCLOSURES: WHERE IT IS NECESSARY FOR DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT. WHEN IT IS NECESSARY FOR A DIVER TO ENTER ANY PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48" IN HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT. WORK IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFTwas $59.51
DIVER: DIVER TENDER DEPTH PAY (SURFACE DIVING): FOOT 221 FT.-DEEPER $5.00 PER FOOT SATURATION DIVING: THE STANDBY RATE SHALL APPLY UNTIL SATURATION STARTS. THE SATURATION DIVING RATE APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS. DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT. PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48" IN HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT. WORK IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE FOR THAT SHIFTwas $59.51
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8-Awas $55.49
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8was $57.70
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 7was $58.84
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 6was $42.50
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 5was $44.73
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 4was $47.37
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Truck Crane Oiler)was $45.12
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Oiler)was $42.89
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Lifting devices)was $49.14
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Truck Crane Oiler)was $45.41
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Oiler)was $43.11
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Lifting devices)was $50.82
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Truck Crane Oiler)was $45.66
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Oiler)was $43.38
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Lifting devices)was $52.64
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 5)was $58.09
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 4)was $59.23
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 3)was $60.37
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 2)was $61.70
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1-A)was $65.43
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1)was $62.96
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 5)was $58.19
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 4)was $59.33
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 3)was $60.47
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 2)was $61.80
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1-A)was $65.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1)was $63.06
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 5was $62.24
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 4was $63.54
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 3was $65.56
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 2was $67.04
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 1was $68.81
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 6was $59.98
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 5was $61.30
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 4was $62.57
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 3was $63.95
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 2was $65.43
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 1was $66.96
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 6was $42.50
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 5was $44.73
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 4was $47.37
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Truck Crane Oiler)was $45.12
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Oiler)was $42.89
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 3 (Lifting devices)was $49.14
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Truck Crane Oiler)was $45.41
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Oiler)was $43.11
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 2 (Lifting devices)was $50.82
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Truck Crane Oiler)was $45.66
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Oiler)was $43.38
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:: GROUP 1 (Lifting devices)was $52.64
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 5)was $58.09
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 4)was $59.23
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 3)was $60.37
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 2)was $61.70
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1-A)was $65.43
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: UNDERGROUND: (GROUP 1)was $62.96
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 5)was $58.19
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 4)was $59.33
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 3)was $60.47
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 2)was $61.80
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1-A)was $65.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1)was $63.06
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 5was $62.24
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 4was $63.54
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 3was $65.56
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 2was $67.04
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA 1:: GROUP 1was $68.81
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 4was $61.30
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Hydraulic)was $59.98
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Cranes)was $64.34
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 2was $66.08
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 1was $68.59
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8-Awas $55.49
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 8was $57.70
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 7was $58.84
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 6was $59.98
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 5was $61.30
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 4was $62.57
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 3was $63.95
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 2was $65.43
OPERATOR: POWER EQUIPMENT, AREA 1:: GROUP 1was $66.96
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS (CALAVERAS AND SAN JOAQUIN COUNTIES)- (2) Establishment Warranty Periodwas $31.59
LABORER, CONSTRUCTION CRAFT LABORERS: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW. GROUP 1 WAGE RATES. "SEWER CLEANER" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACEDwas $31.59
LABORER, WRECKING - AREA A: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (SAN FRANCISCO, AND SAN MATEO COUNTIES)was $36.35
LABORERS:, GUNITE - AREA A: GROUP 4 GUNITE LABORER (SAN FRANCISCO, AND SAN MATEO COUNTIES)was $36.25
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (SAN FRANCISCO, AND SAN MATEO COUNTIES)- (2) Establishment Warranty Periodwas $29.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (SAN FRANCISCO, AND SAN MATEO COUNTIES)- (1) New Constructionwas $36.25
LABORER, WRECKING - AREA A:: GROUP 1 (SAN FRANCISCO, AND SAN MATEO COUNTIES)was $36.50
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". COUNTIES)was $29.94
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (SAN FRANCISCO, AND SAN MATEO COUNTIES)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 2 ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES (SAN FRANCISCO, AND SAN MATEO COUNTIES)was $36.35
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER SAN FRANCISCO, AND SAN MATEO COUNTIESwas $36.50
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)- (2) Establishment Warranty Periodwas $28.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)- (1) New Constructionwas $35.25
LABORER, WRECKING - AREA B: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)was $35.35
LABORER, WRECKING - AREA B: GROUP 1 (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)was $35.50
LABORER, GUNITE - AREA B: GROUP 4 GUNITE LABORER (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)was $35.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 4 (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES) FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". COUNTIES)was $28.94
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)was $35.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 2 ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)was $35.35
LABORER, WRECKING - AREA A:: GROUP 1 (ALAMEDA COUNTY)was $36.50
LABORER, WRECKING - AREA A: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (ALAMEDA COUNTY)was $36.35
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 1- LABORER CLASSIFICATIONS CONSTRUCTION SPECIALIST GROUP: ASPHALT IRONER AND RAKER; CHAINSAW; LASER BEAM IN CONNECTION WITH LABORERS' WORK; CAST-IN- PLACE MANHOLE FORM SETTER; PRESSURE PIPELAYER; DAVIS TRENCHER - 300 OR SIMILAR TYPE (AND ALL SMALL TRENCHERS); BLASTER; DIAMOND DRILLER; MULTIPLE UNIT DRILL; HYDRAULIC DRILL. GROUP 1: ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER (MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES)was $35.50
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (SANTA CLARA COUNTY)- (2) Establishment Warranty Periodwas $29.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (SANTA CLARA COUNTY)- (1) New Constructionwas $36.25
LABORER, WRECKING - AREA A:: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (SANTA CLARA COUNTY)was $36.35
LABORER, WRECKING - AREA A:: GROUP 1 (SANTA CLARA COUNTY)was $36.50
LABORER, GUNITE - AREA A: GROUP 4 GUNITE LABORER (SANTA CLARA COUNTY)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A:: GROUP 1 (SANTA CLARA COUNTY)was $36.50
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW. SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. "SEWER CLEANER" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACEDwas $29.94
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (SANTA CLARA COUNTY)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 2 ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES (SANTA CLARA COUNTY)was $36.35
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (FRESNO, KINGS, AND MADERA COUNTIES)- (2) Establishment Warranty Periodwas $28.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (FRESNO, KINGS, AND MADERA COUNTIES)- (1) New Constructionwas $35.25
LABORER, WRECKING - AREA B:: GROUP 1 (FRESNO, KINGS, AND MADERA COUNTIES)was $35.50
LABORER, WRECKING - AREA B: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (FRESNO, KINGS, AND MADERA COUNTIES)was $35.35
LABORER, GUNITE - AREA B: GROUP 4 GUNITE LABORER (FRESNO, KINGS, AND MADERA COUNTIES)was $35.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW. ABOVE GROUP 1 WAGE RATES. "SEWER CLEANER" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACED. GUNITE LABORER CLASSIFICATIONSwas $28.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (ALAMEDA COUNTY)- (2) Establishment Warranty Periodwas $29.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA A: (ALAMEDA COUNTY)- (1) New Constructionwas $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (FRESNO, KINGS, AND MADERA COUNTIES)was $35.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 2 ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES (FRESNO, KINGS, AND MADERA COUNTIES)was $35.35
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER (FRESNO, KINGS, AND MADERA COUNTIES)was $35.50
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES)- (2) Establishment Warranty Periodwas $28.94
LABORER: GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS - AREA B: (MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES)- (1) New Constructionwas $35.25
LABORER, WRECKING - AREA B: GROUP 2 SEMI-SKILLED WRECKER (SALVAGING OF OTHER BUILDING MATERIALS) (MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES)was $35.35
LABORER, WRECKING - AREA B: GROUP 1- SKILLED WRECKER (REMOVING AND SALVAGING OF SASH, WINDOWS AND MATERIALS)was $35.50
LABORER, GUNITE - AREA B: GROUP 4 Gunite laborer COUNTIES)was $35.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". TUOLUMNE , COUNTIES)was $28.94
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES)was $35.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 2 (ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES)was $35.35
LABORER, CONSTRUCTION CRAFT LABORERS - AREA B: GROUP 1- ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER, BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER INCLUDING LEADE ABATEMENT; COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK; CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER, SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER, ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE (1-1/2" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO SEEDER AND SIMILAR TYPE; JACKHAMMER OPERATOR; JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC AND SIMILAR TYPE MATERIALS (APPLYING MEANS APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS); LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING, LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS, MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS; PAVEMENT BREAKER AND SPADER, INCLUDING TOOL GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE CHECKING IN CONNECTION WITH PIPELAYING); PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF SACKED CONCRETE AND/OR SAND (WET OR DRY) AND GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN, NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED, BULL FLOAT IN CONNECTION WITH LABORERS' WORK; VIBRATOR; HAZARDOUS WASTE WORKER (LEAD REMOVAL); ASBESTOS AND MOLD REMOVAL WORKER (MARIPOSA, MERCED, STANISLAUS, AND TUOLUMNE , COUNTIES)was $35.50
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 4was $61.30
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Hydraulic)was $59.98
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 3 (Cranes)was $64.34
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 2was $66.08
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS - AREA 1:: GROUP 1was $68.59
LABORER, GUNITE - AREA A: GROUP 4 GUNITE LABORER (ALAMEDA COUNTY)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A:: GROUP 1 (ALAMEDA COUNTY)was $36.50
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW. SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. "SEWER CLEANER" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACEDwas $29.94
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (ALAMEDA COUNTY)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 2 ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES (ALAMEDA COUNTY)was $36.35
LABORER: GARDENERS, HORTICULURAL & LANDSCAPE LABORERS - AREA A: (CONTRA COSTA COUNTY)- (2) Establishment Warranty Periodwas $29.94
LABORER: GARDENERS, HORTICULURAL & LANDSCAPE LABORERS - AREA A: (CONTRA COSTA COUNTY)- (1) New Constructionwas $36.25
LABORER, WRECKING - AREA A:: GROUP 1 (CONTRA COSTA COUNTY)was $36.50
LABORER, WRECKING - AREA A: GROUP 2 Semi-skilled wrecker (salvaging of other building materials) (CONTRA COSTA COUNTY)was $36.35
LABORER, GUNITE - AREA A: GROUP 4 GUNITE LABORER (CONTRA COSTA COUNTY)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A:: GROUP 1 (CONTRA COSTA COUNTY)was $36.50
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 4 FINAL CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING INCLUDING BUT NOT LIMITED TO: STREET CLEANER; CLEANING AND WASHING WINDOWS; BRICK CLEANER (JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY). THE CLASSIFICATION "MATERIAL CLEANER" IS TO BE UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL. B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL IS TO BE SALVAGED AND STOCKED TO BE REUSED ON ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD. THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT BE USED IN THE PERFORMANCE OF "FORM STRIPPING, CLEANING AND OILING AND MOVING TO THE NEXT POINT OF ERECTION". LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS SHALL RECEIVE $0.25 PER HOUR ABOVE THE APPLICABLE WAGE RATE. THIS SHALL NOT APPLY TO WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A BELOW. SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE GROUP 1 WAGE RATES. "SEWER CLEANER" MEANS ANY WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND ALL RECENTLY ACTIVE SEWER MANHOLES SHAL RECEIVE $5.00 PER DAY ABOVE GROUP 1 WAGE RATES. MAINTENANCE AND REPAIR TRACK AND ROAD BEDS. ALL EMPLOYEES PERFORMING WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT SHALL APPLY TO CUT AND COVER WORK OF SUBWAY CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN PLACEDwas $29.94
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 3 CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR; GARDENER, HORTICULTURAL AND LANDSCAPE LABORER; JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORER; TEMPORARY AIR AND WATER LINES, VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE ONLY) (CONTRA COSTA COUNTY)was $36.25
LABORER, CONSTRUCTION CRAFT LABORERS - AREA A: GROUP 2 ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE CHIPPING AND GRINDING; CONCRETE LABORER (WET OR DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE, ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS. PRESSURE); LOADING AND UNLOADING, CARRYING AND HAULING OF ALL RODS AND MATERIALS FOR USE IN REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER; SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12 INCHES (CONTRA COSTA COUNTY)was $36.35
SHEET METAL WORKER: (AREA 2)was $64.23