Rate changes

Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.

ClassificationOld totalNew totalΔ/hrHours on jobCost impact
ELEVATOR MECHANIC$107.87$107.87+0.00
ELECTRICIANS CABLE SPLICERS: $2.00 ADDITIONAL PER HOUR. ALL WORK AT VANDENBERG AFB: $3.75 ADDITIONAL PER HOUR.$78.13$79.77+1.64
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE, BACKGROUND-FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, INVENTORY CONTROL SYSTEMS, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEMS, RADIO PAGE, SCHOOL INTERCOM AND SOUND, BURGLAR ALARMS, FIRE ALARM (SEE LAST PARAGRAPH BELOW) AND LOW VOLTAGE MASTER CLOCK SYSTEMS IN COMMERCIAL BUILDINGS. COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND TESTINGS OF CONDUCTORS DETERMINED BY THEIR FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND ENERGY MANAGEMENT SYSTEMS. DOES NOT COVER WORK PERFORMED AT CHINA LAKE NAVAL ORDNANCE TEST STATION. FIRE ALARM WORK SHALL BE PERFORMED AT THE CURRENT INSIDE WIREMAN TOTAL COST PACKAGE$64.18$65.62+1.44

Removed classifications

Painters: (Including Lead Abatement) - (2) Repaintwas $26.40
Painters: (Including Lead Abatement) - (3) Iron & Steelwas $33.12
Painters: (Including Lead Abatement) - (4) High Iron & Steelwas $35.12
LINE CONSTRUCTION - (4) Powdermanwas $51.87