Rogers County, Oklahoma: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Building OK20260052 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $22.18 | $5.06 | $27.24 |
| PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING | $12.22 | $0.00 | $12.22 |
| OPERATOR: LOADER (FRONT END) | $16.18 | $0.00 | $16.18 |
| OPERATOR: GRADER/BLADE | $14.28 | $1.70 | $15.98 |
| OPERATOR: BULLDOZER | $19.34 | $1.90 | $21.24 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $17.64 | $0.38 | $18.02 |
| OPERATOR: ASPHALT PAVER | $16.88 | $0.00 | $16.88 |
| LABORER: PIPELAYER | $12.39 | $0.00 | $12.39 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.00 | $1.91 | $14.91 |
| LABORER: MASON TENDER - BRICK | $12.52 | $0.00 | $12.52 |
| LABORER: COMMON OR GENERAL | $13.23 | $3.95 | $17.18 |
| FORM WORKER | $14.17 | $0.38 | $14.55 |
| ELECTRICIAN: ALARM INSTALLATION | $19.00 | $3.20 | $22.20 |
| ELECTRICIAN (SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION) | $20.66 | $2.64 | $23.30 |
| DRYWALL FINISHER/TAPER | $13.00 | $0.00 | $13.00 |
| CEMENT MASON/CONCRETE FINISHER | $14.26 | $1.27 | $15.53 |
| CAULKER | $20.00 | $1.61 | $21.61 |
| CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $12.38 | $0.00 | $12.38 |
| CARPENTER (DRYWALL HANGING ONLY) | $15.07 | $1.22 | $16.29 |
| BRICKLAYER | $26.92 | $13.09 | $40.01 |
| ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF ALARMS AND SOUND AND COMMUNICATION SYSTEMS) | $38.38 | $12.89 | $51.27 |
| ELECTRICIAN (LOW VOLTAGE WIRING ONLY) | $38.38 | $12.89 | $51.27 |
| ELEVATOR MECHANIC PAID HOLIDAYS: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE TO VACATION PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE | $51.24 | $38.44 | $89.68 |
| IRONWORKER: ORNAMENTAL, REINFORCING AND STRUCTURAL | $30.35 | $16.83 | $47.18 |
| PLUMBER (EXCLUDES HVAC PIPE AND UNIT INSTALLATION) | $36.65 | $16.03 | $52.68 |
| HVAC MECHANIC (INSTALLATION OF HVAC UNIT ONLY, EXCLUDES INSTALLATION OF HVAC PIPE AND DUCT) | $36.65 | $16.03 | $52.68 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION | $36.65 | $16.03 | $52.68 |
| ROOFER | $26.30 | $10.34 | $36.64 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $35.49 | $14.60 | $50.09 |
| TRUCK DRIVER: DUMP AND FLATBED TRUCK | $11.00 | $0.00 | $11.00 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $21.86 | $1.19 | $23.05 |
POWER EQUIPMENT OPERATOR 6 classifications · $46.30 to $57.14 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT | $28.77 | $19.05 | $47.82 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER; SEMI- TRAILER TRUCK DRIVER | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 |
Heavy OK20260030 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | $51.00 | $23.80 | $74.80 |
| IRONWORKER (STRUCTURAL, REINFORCING, AND ORNAMENTAL) | $30.35 | $16.83 | $47.18 |
| TRUCK DRIVER: DUMP TRUCK | $14.64 | $1.71 | $16.35 |
| LABORER: PIPELAYER | $12.94 | $2.42 | $15.36 |
| LABORER: COMMON OR GENERAL | $11.78 | $2.76 | $14.54 |
| FORM WORKER | $11.77 | $0.00 | $11.77 |
| CEMENT MASON/CONCRETE FINISHER | $14.00 | $3.95 | $17.95 |
POWER EQUIPMENT OPERATOR 6 classifications · $46.30 to $57.14 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR: GROUP 6 ROLLER (ASPHALT AND DIRT) | $30.87 | $19.05 | $49.92 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 |
OPERATOR 8 classifications · $14.01 to $29.00 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: TRACKHOE | $18.54 | $2.78 | $21.32 |
| OPERATOR: SCRAPER | $16.00 | $1.55 | $17.55 |
| OPERATOR: MECHANIC | $19.61 | $9.39 | $29.00 |
| OPERATOR: LOADER (FRONT END) | $14.01 | $0.00 | $14.01 |
| OPERATOR: GRADER/BLADE | $17.76 | $3.87 | $21.63 |
| OPERATOR: DRILL | $17.15 | $0.78 | $17.93 |
| OPERATOR: BULLDOZER | $17.98 | $1.75 | $19.73 |
| OPERATOR: BACKHOE/EXCAVATOR | $16.62 | $3.10 | $19.72 |
Highway OK20260017 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (TULSA COUNTY) | $18.01 | $0.00 | $18.01 |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (ROGERS COUNTY) | $14.01 | $0.31 | $14.32 |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (REMAINING COUNTIES) | $16.36 | $0.00 | $16.36 |
| TRUCK DRIVER (WATER TRUCK) | $12.00 | $0.00 | $12.00 |
| TRUCK DRIVER (PICKUP TRUCK) | $12.32 | $0.00 | $12.32 |
| TRUCK DRIVER (OFF THE ROAD TRUCK) | $13.40 | $0.00 | $13.40 |
| TRUCK DRIVER (LOWBOY/FLOAT) | $13.80 | $0.00 | $13.80 |
| TRUCK DRIVER (FLATBED TRUCK) | $14.69 | $0.00 | $14.69 |
| TRUCK DRIVER (DUMP TRUCK) | $13.97 | $0.00 | $13.97 |
| TRAFFIC SIGNAL INSTALLER | $18.04 | $0.00 | $18.04 |
| LABORER, TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS) (TULSA COUNTY) | $10.94 | $0.00 | $10.94 |
| LABORER, TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS) (REMAINING COUNTIES) | $11.05 | $0.00 | $11.05 |
| LABORER, COMMON OR GENERAL (WAGONER) | $10.32 | $0.00 | $10.32 |
| LABORER, COMMON OR GENERAL (TULSA COUNTY) | $10.84 | $0.00 | $10.84 |
| LABORER, COMMON OR GENERAL (ROGERS COUNTY) | $10.14 | $0.00 | $10.14 |
| LABORER, COMMON OR GENERAL (REMAINING COUNTIES) | $10.70 | $0.00 | $10.70 |
| LABORER, COMMON OR GENERAL (CREEK COUNTY) | $10.95 | $0.00 | $10.95 |
| LABORER, ASPHALT RAKER AND SHOVELER (ROGERS COUNTY) | $11.76 | $1.57 | $13.33 |
| LABORER, ASPHALT RAKER AND SHOVELER (REMAINING COUNTIES) | $12.40 | $1.57 | $13.97 |
| LABORER (POWER TOOL OPERATOR (INCLUDES CHIPPING GUNS AND HANDHELD CONCRETE SAWS)) | $12.89 | $0.00 | $12.89 |
| LABORER (PIPELAYER) | $12.35 | $0.00 | $12.35 |
| LABORER (LANDSCAPE) | $8.67 | $0.00 | $8.67 |
| IRONWORKER: REINFORCING | $15.38 | $0.00 | $15.38 |
| IRONWORKER, STRUCTURAL | $14.21 | $0.00 | $14.21 |
| CEMENT MASON/CONCRETE FINISHER (TULSA COUNTY) | $13.44 | $0.00 | $13.44 |
| CEMENT MASON/CONCRETE FINISHER (REMAINING COUNTIES) | $13.36 | $0.00 | $13.36 |
| CARPENTER, INCLUDES FORM WORK, AND CURB LINE FORMSETTING (TULSA COUNTY) | $12.80 | $0.00 | $12.80 |
| CARPENTER, INCLUDES FORM WORK, AND CURB LINE FORMSETTING (ROGERS COUNTY) | $14.82 | $0.00 | $14.82 |
| CARPENTER, INCLUDES FORM WORK, AND CURB LINE FORMSETTING (REMAINING COUNTIES) | $13.24 | $0.00 | $13.24 |
POWER EQUIPMENT OPERATOR 25 classifications · $11.71 to $17.46 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (TULSA COUNTY) | $15.19 | $0.00 | $15.19 |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (ROGERS COUNTY) | $15.11 | $0.00 | $15.11 |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES) | $15.16 | $0.00 | $15.16 |
| POWER EQUIPMENT OPERATOR: (TRENCHER) | $13.87 | $0.00 | $13.87 |
| POWER EQUIPMENT OPERATOR: (TRACTOR/BOX BLADE) | $13.67 | $0.00 | $13.67 |
| POWER EQUIPMENT OPERATOR: (STRIPING MACHINE) | $11.94 | $0.00 | $11.94 |
| POWER EQUIPMENT OPERATOR: (SCRAPER) | $13.34 | $0.00 | $13.34 |
| POWER EQUIPMENT OPERATOR: (ROLLER (DIRT COMPACTION)) | $11.71 | $0.00 | $11.71 |
| POWER EQUIPMENT OPERATOR: (ROLLER (ASPHALT)) | $12.79 | $0.00 | $12.79 |
| POWER EQUIPMENT OPERATOR: (OILER) | $15.28 | $0.00 | $15.28 |
| POWER EQUIPMENT OPERATOR: (MIXER) | $14.43 | $0.00 | $14.43 |
| POWER EQUIPMENT OPERATOR: (MILLING MACHINE) | $14.56 | $0.00 | $14.56 |
| POWER EQUIPMENT OPERATOR: (MECHANIC) | $17.46 | $0.00 | $17.46 |
| POWER EQUIPMENT OPERATOR: (LOADER (FRONT END)) | $13.81 | $0.00 | $13.81 |
| POWER EQUIPMENT OPERATOR: (GRADER/BLADE) | $16.68 | $0.00 | $16.68 |
| POWER EQUIPMENT OPERATOR: (EXCAVATOR) | $14.99 | $0.00 | $14.99 |
| POWER EQUIPMENT OPERATOR: (DISTRIBUTOR TRUCK) | $13.34 | $0.00 | $13.34 |
| POWER EQUIPMENT OPERATOR: (CRANE) | $17.45 | $0.00 | $17.45 |
| POWER EQUIPMENT OPERATOR: (CONCRETE SAW) | $11.94 | $0.00 | $11.94 |
| POWER EQUIPMENT OPERATOR: (CONCRETE PAVING MACHINE) | $14.11 | $0.00 | $14.11 |
| POWER EQUIPMENT OPERATOR: (BULLDOZER) | $14.28 | $0.00 | $14.28 |
| POWER EQUIPMENT OPERATOR: (BROOM) | $11.97 | $0.00 | $11.97 |
| POWER EQUIPMENT OPERATOR: (BOBCAT/SKID LOADER) | $12.24 | $0.00 | $12.24 |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVING MACHINE) | $13.95 | $2.75 | $16.70 |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVER SCREED) | $12.96 | $0.00 | $12.96 |
Residential OK20260081 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER | $25.92 | $11.89 | $37.81 |
| PLUMBER | $33.14 | $0.00 | $33.14 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $17.02 | $10.00 | $27.02 |
| LABORER: COMMON OR GENERAL | $12.50 | $0.00 | $12.50 |
| IRONWORKER, STRUCTURAL | $17.10 | $4.22 | $21.32 |
| ELECTRICIAN | $19.08 | $0.00 | $19.08 |
| CEMENT MASON/CONCRETE FINISHER | $18.57 | $0.00 | $18.57 |
| CARPENTER | $14.98 | $0.00 | $14.98 |
Get an email when rates change here
One watch per determination above; every email includes a stop link. Bidding a specific job? Pin it to your bid date instead.