Missoula County, Montana: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Building MT20260063 rev 2
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| HEAT AND FROST INSULATOR | $43.81 | $21.87 | $65.68 |
| BOILERMAKER | $38.75 | $32.31 | $71.06 |
| BRICKLAYER | $33.11 | $16.69 | $49.80 |
| MILLWRIGHT. ZONE DEFINITION: THE HOURLY RATE APPLICABLE TO EACH PROJECT IS DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL ROUTE FROM THE COUNTY COURTHOUSE OF THE FOLLOWING TOWNS TO THE CETER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, LEWISTON, MILES CITY, AND MISSOULA ZONE 1: 0 TO 30 MILES - BASE RATE ZONE 2: 31 TO 60 MILES - $4.00 ZONE 3: OVER 60 MILES - $6.00 | $33.00 | $13.57 | $46.57 |
| CARPENTER: INCLUDING DRYWALL HANGING, METAL STUD INSTALLATION, AND FORMWORK. ZONE DEFINITION: THE HOURLY RATE APPLICABLE TO EACH PROJECT IS DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL ROUTE FROM THE COUNTY COURTHOUSE OF THE FOLLOWING TOWNS TO THE CETER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, LEWISTON, MILES CITY, AND MISSOULA 31 TO 60 MILES - $4.00 ZONE 3: OVER 60 MILES - $6.00 | $32.05 | $15.02 | $47.07 |
| ELECTRICIAN | $40.71 | $17.94 | $58.65 |
| ELEVATOR MECHANIC | $67.61 | $38.44 | $106.05 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (2) EXCAVATOR ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $32.88 | $16.20 | $49.08 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (1) CRANE, FORKLIFT, FRONT END LOADER ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $31.51 | $16.20 | $47.71 |
| IRONWORKER, STRUCTURAL, REINFORCING AND ORNAMENTAL | $32.08 | $29.06 | $61.14 |
| LABORER, ZONE 1: MASON TENDER-BRICK ZONE DEFINITIONS FOR LABORERS THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE COUNTY COURTHOUSE OF THE FOLLOWING LISTED TOWN TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, HELENA, GREAT FALLS, MISSOULA, KALISPELL TRAVEL ZONES: ZONE 1: 0 TO 30 MILES, BASE PAY ZONE 2: MILES, ADD $4.85 TO BASE PAY | $23.05 | $12.72 | $35.77 |
| LABORER, ZONE 1: COMMON OR GENERAL ZONE DEFINITIONS FOR LABORERS THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE COUNTY COURTHOUSE OF THE FOLLOWING LISTED TOWN TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, HELENA, GREAT FALLS, MISSOULA, KALISPELL TRAVEL ZONES: ZONE 1: 0 TO 30 MILES, BASE PAY ZONE 2: MILES, ADD $4.85 TO BASE PAY | $23.05 | $12.72 | $35.77 |
| PAINTER: BRUSH AND SPRAY | $18.35 | $6.84 | $25.19 |
| PLUMBER, INCLUDES HVAC PIPE INSTALLATION | $42.80 | $17.28 | $60.08 |
| PIPEFITTER, EXCLUDES HVAC PIPE INSTALLATION | $42.80 | $17.28 | $60.08 |
| ROOFER | $30.97 | $13.46 | $44.43 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $39.97 | $24.40 | $64.37 |
| SHEET METAL WORKER (HVAC DUCT AND SYSTEM INSTALLATION ONLY) | $40.07 | $22.07 | $62.14 |
| PAINTER: ROLLER | $17.00 | $0.00 | $17.00 |
| OPERATOR: BACKHOE | $20.56 | $6.35 | $26.91 |
Heavy MT20260067 rev 2
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $38.75 | $32.31 | $71.06 |
| CARPENTER (INCLUDING FORMWORK). ZONE DEFINITION: THE HOURLY RATE APPLICABLE TO EACH PROJECT IS DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL ROUTE FROM THEC OUNTY COURTHOUSE OF THE FOLLOWING TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, LEWISTON, MILES CITY, AND MISSOULA. ZONE 1: 0 TO 30 MILES-BASE RATE. ZONE 2: 31 TO 60 MILES -$4.00. ZONE 3: OVER 60 MILESE - $6.00 | $36.49 | $14.33 | $50.82 |
| ELECTRICIAN | $40.71 | $17.94 | $58.65 |
| IRONWORKER: REINFORCING AND STRUCTURAL | $32.08 | $29.06 | $61.14 |
| PLUMBER | $39.38 | $16.23 | $55.61 |
| TRUCK DRIVER: DUMP TRUCK | $19.38 | $4.74 | $24.12 |
| PAINTER: BRUSH AND SPRAY | $25.00 | $0.00 | $25.00 |
| OPERATOR: LOADER (FRONT END) | $22.67 | $6.54 | $29.21 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $25.67 | $8.05 | $33.72 |
| OPERATOR: BACKHOE | $22.12 | $8.37 | $30.49 |
| OPERATOR: ASPHALT ROLLER | $22.39 | $3.96 | $26.35 |
| LABORER: COMMON OR GENERAL | $16.91 | $9.08 | $25.99 |
| TRUCK DRIVER (3) WATER TRUCK ZONE A. ZONE B (30-60 MILES FROM COUNTY COURTHOUSE OF LISTED CITIES*): ADD $3.05 PER HOUR TO ZONE A RATES ZONE C (OVER 60 MILES FROM COUNTY COURTHOUSE OF LISTED CITIES*): ADD $4.85 PER HOUR TO ZONE A RATES | $32.88 | $13.98 | $46.86 |
| TRUCK DRIVER (2) WATER TRUCK ZONE A. ZONE B (30-60 MILES FROM COUNTY COURTHOUSE OF LISTED CITIES*): ADD $3.05 PER HOUR TO ZONE A RATES ZONE C (OVER 60 MILES FROM COUNTY COURTHOUSE OF LISTED CITIES*): ADD $4.85 PER HOUR TO ZONE A RATES | $32.88 | $13.98 | $46.86 |
POWER EQUIPMENT OPERATOR 7 classifications · $33.87 to $58.43 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR:, ZONE 1: (7) CRANES, 150 TONS TO INCLUDING 250 TONS (ADD $1.00 FOR EVERY 100 TONS OVER 250 TONS); CRANE, STIFF-LEG OR DERRICK; HELICOPTER HOIST; CRANE, TOWER (ALL). ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $42.23 | $16.20 | $58.43 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (6)CRANES, 75 TONS TO AND INCL. 149 TONS; WHIRLEY CRANES. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $41.15 | $16.20 | $57.35 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (5)CRANES, 45-74 TONS. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $40.07 | $16.20 | $56.27 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (4)CRANES, 25-44 TONS. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $38.98 | $16.20 | $55.18 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (3) MECHANIC, SCRAPER. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $24.34 | $10.40 | $34.74 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (2) EXCAVATOR, CRANE OILER. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $23.94 | $10.40 | $34.34 |
| POWER EQUIPMENT OPERATOR: ZONE 1: (1) A-FRAME TRUCK CRANE, FORKLIFT, OILER (EXCEPT CRANE). ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $23.47 | $10.40 | $33.87 |
Highway MT20260080 rev 3
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER: Carpenter | $43.78 | $17.07 | $60.85 |
| CARPENTER: Millwright | $49.79 | $20.79 | $70.58 |
| CEMENT MASON/CONCRETE FINISHER | $44.98 | $20.50 | $65.48 |
| DIVER: Diver Tender (The Tender shall receive 2 hours at straight time pay rate per shift for dressing and/or undressing when work is done in hyperbaric conditions. Depth Pay (Surface Diving): 0-20 ft. Free Zone; >20-100 ft. $2.00 per ft.; >100-150 ft | $3.00 | $4.00 | $7.00 |
| ft.; >220+ ft | $5.00 | $20.22 | $25.22 |
| DIVER: Diving (Diving in Enclosures (Diver Only): 0-25 ft. Free Zone; >25-300 ft | $1.00 | $20.22 | $21.22 |
| DIVER: Stand-By | $60.76 | $20.22 | $80.98 |
| ELECTRICIAN | $48.31 | $22.00 | $70.31 |
| ELECTRICIAN (LINE CONSTRUCTION): Equipment Operator | $55.14 | $23.37 | $78.51 |
| ELECTRICIAN (LINE CONSTRUCTION): Groundman | $37.43 | $21.85 | $59.28 |
| ELECTRICIAN (LINE CONSTRUCTION): Lineman | $62.60 | $24.46 | $87.06 |
| IRONWORKER: Reinforcing Iron and Rebar Workers | $42.70 | $28.92 | $71.62 |
| IRONWORKER: Structural Iron and Steel Workers | $38.31 | $27.91 | $66.22 |
| LABORER: Group 1 Flag Person for Traffic Control | $30.48 | $13.60 | $44.08 |
| LABORER: Group 2 General Labor; Asbestos Removal; Burning Bar; Bucket Man; Carpenter Tender; Caisson Worker; Cement Mason Tender; Cement Handler (dry); Chuck Tender; Choker Setter; Concrete Worker; Curb Machine-Lay Down; Crusher and Batch Worker; Heater Tender; Fence Erector; Landscape Laborer; Landscaper; Lawn Sprinkler Installer; Pipe Wrapper; Pot Tender; Powderman Tender; Rail and Truck Loaders and Unloaders; Riprapper; Sign Erection; Guardrail and Jersey Rail; Spike Driver; Stake Jumper; Signalman: Tail Hoseman; Tool Checker and Houseman and Traffic Control Worker | $33.96 | $13.60 | $47.56 |
| LABORER: Group 3 Concrete Vibrator; Dumpman (Grademan); Equipment Handler; Geotextile and Liners; High-Pressure Nozzleman; Jackhammer (Pavement Breaker) Non-Riding Rollers; Pipelayer; Posthole Digger (power); Power Driven Wheelbarrow; Rigger; Sandblaster; Sod-Cutter-power and Tampers | $34.21 | $13.60 | $47.81 |
| LABORER: Group 4 Hod Carrier; Water Well Laborer; Blaster; Wagon Driller; Asphalt Raker; Cutting Torch; Grade Setter; High- Scaler; Power Saws (Faller & Concrete); Powderman; Rock & Core Drill; Track or Truck Mounted Wagon Drill and Welder incl. Air Arc | $35.33 | $13.60 | $48.93 |
| PAINTER | $39.60 | $14.12 | $53.72 |
| PILE BUCKS | $43.78 | $17.07 | $60.85 |
| TRUCK DRIVER: Group 1 Pilot Car | $31.03 | $13.83 | $44.86 |
| TRUCK DRIVER: Group 2 Combination Truck and Concrete Mixer and Transit Mixer; Dry Batch Trucks; Distributor Driver; Dumpman; Dump Trucks and Similar Equipment; Dumpster; Flat Trucks; Lumber Carriers; Lowboys; Pickup; Powder Truck Driver; Power Boom; Serviceman; Service Truck/Fuel Truck/Tireperson; Truck Mechanic; Trucks with Power Equipment; Warehouseman, Partsman, Cardex and Warehouse Expeditor; Water Trucks | $39.31 | $13.83 | $53.14 |
POWER EQUIPMENT OPERATOR 7 classifications · $49.77 to $60.20 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR: GROUP 1 Air Compressor; Auto Fine Graders; Belt Finishing; Boring Machine (small); Cement Silo; Crane, A-Frame Truck Crane; Crusher Conveyor; DW-10, 15, and 20 Tractor Roller; Farm Tractor; Forklift; Form Grader; Front End Loader Under 1 CU Yard; Heavy Duty Drills; Herman Nelson Heater; Mulching Machine; Oiler, All Except Cranes & Shovels; Pumpman | $35.72 | $14.05 | $49.77 |
| POWER EQUIPMENT OPERATOR: GROUP 2 Air Doctor; Backhoe/Excavator/Shovel up to and including 3 CU Yard; Bit Grinder; Bituminous Paving Travel Plant; Boring Machine Large; Broom, Self-Propelled; Concrete Travel Batcher; Concrete Float & Spreader; Concrete Bucket Dispatcher; Concrete Finish Machine; Concrete Conveyor; Distributor; Dozer; Rubber-Tired, Push & Side Boom; Elevating Grader/Gradall; Field Equipment Serviceman; Front End Loader 1 CU Yard to including 5 CU Yard; Grade Setter; Heavy Duty Drills, All Types; Hoist/Tugger, All; Hydra lift Forklifts & Similar; Industrial Locomotive; Motor Patrol (except finish); Mountain Skidder; Oiler, Cranes\Shovels; Pavement Breaker, EMSCO; Power Saw, Self-Propelled; Pugmill; Pumpcrete\Grout Machine; Punch Truck; Roller, Other Than Asphalt; Roller, Sheepsfoot (Self-Propelled); Roller, 25 Tons and Over; Ross Carrier; Rotomill Under 6 Ft; Trenching Machine; Washing/Screening Plant | $38.00 | $14.05 | $52.05 |
| POWER EQUIPMENT OPERATOR: GROUP 3 Asphalt Paving Machine; Asphalt Screed; Backhoe/Excavator/Shovel Over 3 CU Yard; Cableway Highline; Concrete Batch Plant; Concrete Curing Machine; Concrete Pump; Cranes; Creter; Cranes, Electric Overhead; Cranes 24 Tons and Under; Curb Machine/Slip Form Paver; Finish Dozer; Front End Loader Over 5 CU Yard; Mechanic/Welder; Pioneer Dozer; Roller Asphalt (Breakdown & Finish); Rotomill, Over 6 FT; Scraper, Single, Twin or Pulling Belly Dump; Yo-Yo Cat Haul Truck, Articulating Trucks, Vac Truck | $39.27 | $14.05 | $53.32 |
| POWER EQUIPMENT OPERATOR: GROUP 4 Asphalt/Hot Plant Operator, Cranes, 25 Tons up to and incl. 44 Tons; Crusher Operator; Finish Motor Patrol; Finish Scraper | $40.60 | $14.05 | $54.65 |
| POWER EQUIPMENT OPERATOR: GROUP 5 Cranes, 45 Tons up to and incl. 74 Tons | $41.85 | $14.05 | $55.90 |
| POWER EQUIPMENT OPERATOR: GROUP 6 Cranes, 75 Tons up to and incl. 149 Tons; Crane, Whirley (All) | $43.20 | $14.05 | $57.25 |
| POWER EQUIPMENT OPERATOR: GROUP 7 Cranes, 150 Tons up to and incl. 250 Tons; Cranes, over 250 tons-add $1.00 for every 100 tons over 250 tons; Crane, Tower (All); Crane Stiff-Leg or Derrick; Helicopter Hoist | $46.15 | $14.05 | $60.20 |
Residential MT20260005 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVERS: (3) COMBINATION TRUCK, CONCRETE MIXER, TRANSIT MIXER | $11.10 | $1.66 | $12.76 |
| TRUCK DRIVERS: (2) FLATBED: (OVER 3 TONS) | $11.20 | $1.66 | $12.86 |
| TRUCK DRIVERS: (2) FLATBED: (3 TONS AND UNDER) | $11.00 | $1.66 | $12.66 |
| TRUCK DRIVERS: (1) PICKUP | $10.95 | $1.66 | $12.61 |
| TERRAZZO & TILE SETTER | $14.45 | $1.45 | $15.90 |
| SHEET METAL WORKER | $15.38 | $2.05 | $17.43 |
| ROOFER | $13.65 | $1.80 | $15.45 |
| POWER EQUIPMENT OPERATOR: FRONT END LOADER: 1 TO 3 CU YD | $12.96 | $2.42 | $15.38 |
| POWER EQUIPMENT OPERATOR: FRONT END LOADER: 1 CU YD OR LESS | $12.67 | $2.42 | $15.09 |
| PLUMBER | $15.78 | $1.60 | $17.38 |
| PLASTERER | $10.50 | $1.10 | $11.60 |
| PAINTER | $10.93 | $1.38 | $12.31 |
| LABORERS: UNSKILLED | $9.32 | $1.20 | $10.52 |
| LABORERS: (PIPELAYER) | $9.72 | $1.20 | $10.92 |
| IRONWORKER | $17.18 | $6.18 | $23.36 |
| ELECTRICIAN | $13.10 | $2.49 | $15.59 |
| CEMENT MASON/CONCRETE FINISHER | $10.50 | $1.10 | $11.60 |
| CARPENTER | $13.03 | $3.31 | $16.34 |
| BRICKLAYER | $14.45 | $1.45 | $15.90 |
Get an email when rates change here
One watch per determination above; every email includes a stop link. Bidding a specific job? Pin it to your bid date instead.