Building MA20260001 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TELEDATA SYSTEM INSTALLER (BRISTOL (ATTLEBORO, NORTH ATTLEBORO, SEEKONK)) | $42.09 | $19.71 | $61.80 |
| INSULATOR/ASBESTOS WORKER (ZONE B) ZONE B- BARNSTABLE COUNTY (BARNSTABLE, BOURNE, FALMOUTH, MASHPEE, SANDWICH), BRISTOL COUNTY (ALL CITIES EXCEPT EASTON),AND NORFOLK COUNTY (BELLINGHAM, FRANKLIN, PLAINVILLE) | $55.45 | $36.63 | $92.08 |
| INSULATOR/ASBESTOS WORKER (ZONE A) ZONE A- BARNSTABLE COUNTY (BREWSTER, CHATHAM, DENNIS, EASTHAM, HARWICH, ORLEANS, PROVINCETOWN, TRURO, WELLFLEET, YARMOUTH) BRISTOL COUNTY (EASTON), MIDDLESEX COUNTY, AND NORFOLK COUNTY (AVON, BRAINTREE, BROOKLINE, CANTON, COHASSET, DEDHAM, DOVER, FOXBOROUGH, HOLBROOK, MEDFIELD, MEDWAY, MILLIS, MILTON, NEEDHAM, NORFOLK, NORWOOD, QUINCY, RANDOLPH, SHARON, STOUGHTON, WALPOLE, WELLESLEY, WESTWOOD, WEYMOUTH) | $55.45 | $36.63 | $92.08 |
| HAZARDOUS MATERIAL HANDLER: INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS WHETHER THEY CONTAIN ASBESTOS OR NOT (BARNSTABLE (BREWSTER, CHATHAM, DENNIS, EASTHAM, HARWICH, ORLEANS, PROVINCETOWN, TRURO, WELLFLEET AND YARMOUTH); BRISTOL (EASTON); ESSEX; MIDDLESEX; NORFOLK (AVON, BRAINTREE, BROOKLINE, CANTON, COHASSET, DEDHAM, DOVER, FOXBORO, HOLBROOK, HULL, MEDFIELD, MEDWAY, MILLIS, MILTON, NEEDHA | $55.45 | $36.63 | $92.08 |
| INSULATOR/ASBESTOS WORKER: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS | $55.45 | $36.63 | $92.08 |
| BOILERMAKER | $50.62 | $28.82 | $79.44 |
| BRICKLAYER, CEMENT MASON, PLASTERER (FOXBORO CHAPTER BRISTOL (ATTLEBORO, BERKLEY, DIGHTON, MANSFIELD, NORTH ATTLEBORO, NORTON, RAYNHAM, REHOBOTH, SEEKONK, TAUNTON) AND NORFOLK (BELLINGHAM, CANTON, DEDHAM, FOXBORO, FRANKLIN, NORFOLK, NORWOOD, PLAINVILLE, SHARON, WALPOLE, WESTRWOOD, WRENTHAM) COUNTIES) | $60.26 | $33.71 | $93.97 |
| BRICKLAYER AND PLASTERER (LOWELL CHAPTER MIDDLESEX (ACTON, ASBY, AYER, BEDFORD, BILLERICA, BOXBORO, CARLISLE, CHEMSFORD, DRACUT, DUNSTBLE, FT. DENVENS, GROTON, LITTLETON, LOWELL, NORTH ACTON, PEPPERELL, SHIRLEY, SOUTH ACTON, TEWKSBURY, TOWNSEND, TYNGSBORO, WEST ACTON, WESTFORD, WILMINGTON)) | $60.26 | $33.71 | $93.97 |
| BRICKLAYER (LOWELL CHAPTER MIDDLESEX (ASHLAND, FRAMINGHAM, HOLLISTON, HOPKINTON, HUDSON, MAYNARD, NATICK, SHERBVORN, STOW); AND NORFOLK (MEDFIELD, MEDWAY,MILLIS)) | $60.26 | $33.71 | $93.97 |
| TERRAZZO FINISHER | $63.44 | $37.33 | $100.77 |
| MARBLE, TILE & TERRAZZO WORKERS | $64.52 | $37.51 | $102.03 |
| MARBLE & TILE FINISHER | $49.32 | $35.26 | $84.58 |
| BRICKLAYER (BOSTON CHAPTER MIDDLESEX (ARLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, SOMERVILLE); NORFOLK (BROOKLINE, MILTON); AND SUFFOLK) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, CEMENT MASON AND PLASTERER (LYNN CHAPTER ESSEX (AMESBURY, ANDOVER, BEVERLY, BOXFORD, DANVERS, ESSEX, GEORGETOWN, GLOUCESTER, GROVELAND, HAMILTON, HAVERHILL, IPSEWICH, LAWRENCE, LYNN, LYNNFIELD, MANCHESTER, MARBLEHEAD, MERRIMAC, METHUEN, MIDDLETON, NAHANT, NEWBURY, NEWBURYPORT, NORTH ANDOVER, PEABODY, ROCKPORT, ROWLEY, SALISBURY, SALEM, SAUGUS, SWAMPSCOTT, TOPSFIELD WAKEFIELD, WENHAM, WEST NEWBURY); AND MIDDLESEX (READING, NORTH READING, WAKEFIELD)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER AND PLASTERER (WALTHAM CHAPTER MIDDLESEX (BELMONT, BURLINGTON, CONCORD, LEXINGTON, LINCOLN, STONEHAM, SUDBURY, WALTHAM, WATERTOWN, WAYLAND, WESTON, WINCHESTER, WOBURN)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, CEMENT MASON AND PLASTERER (NEWTON CHAPTER MIDDLESEX (NEWTON) AND NORFOLK (DOVER, NEEDHAM, WELLESLEY)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, CEMENT MASON AND PLASTERER (NEW BEDFORD FARHAVEN, FALL RIVER, FREETOWN, NEW BEDFORD, SOMERSET, SWANSEA, WESTPORT); DUKES; AND NANTUCKET COUNTIES) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, CEMENT MASON AND PLASTERER (QUINCY CHAPTER NORFOLK COUNTY (AVON, BRAINTREE, COHASSET, HOLBROOK, QUINCY, RANDOLPH, SOUGHTON, WEYMOUTH)) | $64.50 | $37.54 | $102.04 |
| PILEDRIVERMAN (SUFFOLK (ALL OF COUNTY); AND THOSE AREAS OF BARNSTABLE, BRISTOL, ESSEX, MIDDLESEX & NORFOLK COUNTIES SITUATED INSIDE BOSTON BELTWAY (I-495) AND NORTH OF CAPE COD CANAL. ALL OF DUKES AND NANTUCKET COUNTIES) | $55.79 | $35.47 | $91.26 |
| PILEDRIVERMAN (THE AREAS OF BARNSTABLE, BRISTOL, AND NORFOLK COUNTIES SITUATED OUTSIDE BOSTON BELTWAY (I-495) AND SOUTH OF CAPE COD CANAL) | $55.79 | $35.47 | $91.26 |
| PILEDRIVERMAN (THOSE AREAS OF ESSEX AND MIDDLESEX COUNTIES SITUATED OUTSIDE BOSTON BELTWAY (I-495)) | $49.19 | $35.47 | $84.66 |
| CARPENTER (MIDDLESEX (BELMONT, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, SOMERVILLE); NORFOLK (BROOKLINE, DEDHAM, MILTON); AND SUFFOLK) | $61.19 | $31.55 | $92.74 |
| CARPENTER (BRISTOL (ATTLEBOROUGH, NORTH ATTLEBOROUGH); ESSEX; MIDDLESEX (EXCEPT BELMONT, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, SOMERVILLE); AND NORFOLK (BELLINGHAM, CANTON, FOXBORO, FRANKLIN, MEDFIELD, MEDWAY, MILLIS, NEEDHAM, NORFOLK, NORWOOD, PLAINVILLE, SHARON, WALPOLE, WELLESLEY, WESTWOOD, WRENTHAM)) | $50.10 | $31.45 | $81.55 |
| CARPENTER (NORFOLK COUNTY (BRAINTREE, COHASSETT, SCITUATE, WEYMOUTH, QUINCY)) | $50.10 | $31.45 | $81.55 |
| CARPENTER (DUKES; NANTUCKET) | $46.43 | $28.35 | $74.78 |
| CARPENTER (BARNSTABLE; BRISTOL (EXCEPT ATTLEBORO & NORTH ATTLEBORO); AND NORFOLK (AVON, HOLBROOK, RANDOLPH, STOUGHTON) COUNTIES) | $39.28 | $27.90 | $67.18 |
| MILLWRIGHT (SUFFOLK COUNTY) | $50.47 | $33.50 | $83.97 |
| MILLWRIGHT (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET AND NORFOLK COUNTIES) | $45.03 | $33.25 | $78.28 |
| FLOOR LAYER: CARPET (MIDDLESEX (BELMONT, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, SOMERVILLE); NORFOLK (BROOKLINE, DEDHAM, MILTON); AND SUFFOLK) | $57.49 | $31.75 | $89.24 |
| FLOOR LAYER: CARPET (BRISTOL; ESSEX; MIDDLESEX (EXCEPT BELMONT, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, SOMERVILLE); REMAINDER OF NORFOLK COUNTY) | $57.49 | $31.75 | $89.24 |
| FLOOR LAYER: CARPET (BARNSTABALE; DUKES; AND NANTUCKET) | $49.18 | $31.75 | $80.93 |
| TELEDATA SYSTEM INSTALLER (MIDDLESEX (ASHBY, ASHLAND, AYER, FT. DEVENS, GROTON, HOPKINTON, HUDSON, MARLBORO, PEPPERELL, SHIRLEY, STOW, TOWNSEND)) | $36.12 | $34.51 | $70.63 |
| ELECTRICIAN (MIDDLESEX (ASHBY, ASHLAND, AYER, FT. DEVENS, GROTON, HOPKINTON, HUDSON, MARLBORO, PEPPERELL, SHIRLEY, STOW, TOWNSEND)) | $48.16 | $36.20 | $84.36 |
| ELECTRICIAN (BRISTOL (ATTLEBORO, NORTH ATTLEBORO, SEEKONK)) | $56.11 | $24.74 | $80.85 |
| TELEDATA SYSTEM INSTALLER (ESSEX; MIDDLESEX (EXCLUDING ASHBY, ASHLAND, AYER, FT. DEVENS, GROTON, HOPKINTON, HUDSON, MARLBORO, PEPPERELL, SHIRLEY, STOW, TOWNSEND); NORFOLK (EXCLUDING AVON, HOLBROOK, PLAINVILLE, RANDOLPH, STOUGHTON) SUFFOLK) | $52.94 | $34.74 | $87.68 |
| ELECTRICIAN (ESSEX (AMESBURY, ANDOVER, BOXFORD, GEORGETOWN, GROVELAND, HAVERHILL, LAWRENCE, MERRIMAC, METHUEN, NEWBURY, NEWBURYPORT, NORTH ANDOVER, ROWLEY, SALISBURY, WEST NEWBURY); MIDDLESEX (BEDFORD, BILLERICA, BOXBORO, BURLINGTON, CARLISLE, CHELMSFORD, DRACUT, DUNSTABLE LITTLETON, LOWELL, NORTH READING, TEWKSBURY, TYNGSBORO, WESTFORD, WILMINGTON)) | $66.17 | $37.08 | $103.25 |
| ELECTRICIAN (ESSEX (BEVERLY, DANVERS, ESSEX, GLOUCESTER, HAMILTON, IPSWICH, MANCHESTER, MARBLEHEAD, MIDDLETON, PEABODY, ROCKPORT, SALEM, TOPSFIELD, WENHAM)) | $66.17 | $37.08 | $103.25 |
| ELECTRICIAN (ESSEX (LYNN, LYNNFIELD, NAHANT, SAUGUS, SWAMPSCOTT); MIDDLESEX (ACTON, ARLINGTON, BELMONT, CAMBRIDGE, CONCORD, EVERETT, FRAMINGHAM, HOLLISTON, LEXINGTON, LINCOLN, MALDEN, MAYNARD, MEDFORD, MELROSE, NATICK, NEWTON, READING, SHERBORN, SOMERVILLE, STONEHAM, SUDBURY, WAKEFIELD, WALTHAM, WATERTOWN, WAYLAND, WESTON, WINCHESTER, WOBURN); NORFOLK (BELLINGHAM, BRAINTREE, BROOKLINE, CANTON, COHASSET, DEDHAM, DOVER, FOXBORO, FRANKLOIN, MEDFIELD, MEDWAY, MILLIS, MILTON, NEEDHAM, NORFOLK, NORWO | $66.17 | $37.08 | $103.25 |
| LINE CONSTRUCTION: LINEMAN A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY AND COLUMBUS DAY, PROVIDED THE EMPLOYEE HAS BEEN EMPLOYED 5 WORKING DAYS PRIOR TO ANY ONE OF THE LISTED HOLIDAYS | $58.41 | $30.19 | $88.60 |
| LINE CONSTRUCTION: GROUNDMAN A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY AND COLUMBUS DAY, PROVIDED THE EMPLOYEE HAS BEEN EMPLOYED 5 WORKING DAYS PRIOR TO ANY ONE OF THE LISTED HOLIDAYS | $32.13 | $12.70 | $44.83 |
| LINE CONSTRUCTION: EQUIPMENT OPERATOR A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY AND COLUMBUS DAY, PROVIDED THE EMPLOYEE HAS BEEN EMPLOYED 5 WORKING DAYS PRIOR TO ANY ONE OF THE LISTED HOLIDAYS | $49.65 | $26.72 | $76.37 |
| LINE CONSTRUCTION: CABLEMAN A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY AND COLUMBUS DAY, PROVIDED THE EMPLOYEE HAS BEEN EMPLOYED 5 WORKING DAYS PRIOR TO ANY ONE OF THE LISTED HOLIDAYS | $58.41 | $30.19 | $88.60 |
| ELECTRICIAN (BARNSTABLE; BRISTOL (EXCEPT ATTLEBORO, NORTH ATTLEBORO, SEEKONK); DUKES; NANTUCKET AND NORFOLK (AVON, HALBROOK, PLAINVILLE, RANDOLPH, STOUGHTON)) | $50.02 | $31.05 | $81.07 |
| TELEDATA SYSTEM INSTALLER (BARNSTABLE; BRISTOL (EXCEPT ATTLEBORO, NORTH ATTLEBORO, SEEKONK); DUKES; NANTUCKET AND NORFOLK (AVON, HALBROOK, PLAINVILLE, RANDOLPH, STOUGHTON)) | $42.52 | $28.47 | $70.99 |
| ELEVATOR MECHANIC | $74.17 | $38.44 | $112.61 |
| IRONWORKERS:: (AREA 2) | $53.46 | $37.67 | $91.13 |
| IRONWORKERS:: (AREA 1) | $57.87 | $37.67 | $95.54 |
| IRONWORKER (MIDDLESEX (ASHBY, ASHLAND, AYER, BOXBORO, HOLLISTON, HOPKINTON, HUDSON, MARLBORO, SHIRLEY, STOW, TOWNSEND); NORFOLK (MEDWAY)) | $57.57 | $37.67 | $95.24 |
| IRONWORKER (BARNSTABLE; BRISTOL (ACUSHNET, ATTLEBORO, BERKLEY, DARTMOUTH, DIGHTON, FAIRHAVEN, FALL RIVER, FREETOWN, MANSFIELD, NEW BEDFORD, NORTH ATTLEBORO, NORTON, RAYNHAM, REHOBOTH, SEEKONK, SOMERSET, SWANSEA, TAUNTON, WESTPORT); DUKES; NANTUCKET; NORFOLK (BILLINGHAM, FRANKLIN, PLAINVILLE, WRENTHAM)) | $43.03 | $33.53 | $76.56 |
| PLASTERER TENDER | $38.95 | $29.70 | $68.65 |
| PLASTERER TENDER (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER ISLAND, NUT ISLAND); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| PLASTERER TENDER (BARNSTABLE, BRISTOL, DUKES, ESSEX, NANTUCKET, MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE DEDHAM AND MILTON) COUNTIES) | $38.95 | $29.70 | $68.65 |
| GLAZIER (BARNSTABLE, BRISTOL, DUKES, AND NANTUCKET COUNTIES) | $43.13 | $21.00 | $64.13 |
| PAINTER SPRAY, SANDBLAST (REPAINT) | $45.72 | $36.00 | $81.72 |
| PAINTER SPRAY, SANDBLAST (NEW CONSTRUCTION) | $47.66 | $36.00 | $83.66 |
| PAINTER BRUSH, TAPER (REPAINT) | $44.32 | $36.00 | $80.32 |
| PAINTER BRUSH, TAPER (NEW CONSTRUCTION) | $46.26 | $36.00 | $82.26 |
| PAINTER SPRAY, SANDBLAST (REPAINT) | $45.72 | $36.00 | $81.72 |
| PAINTER SPRAY, SANDBLAST (NEW CONSTRUCTION) | $47.66 | $36.00 | $83.66 |
| PAINTER BRUSH, TAPER (REPAINT) | $44.32 | $36.00 | $80.32 |
| PAINTER BRUSH, TAPER (NEW CONSTRUCTION) | $46.26 | $36.00 | $82.26 |
| GLAZIER (ESSEX; MIDDLESEX; NORFOLK; SUFFOLK) | $46.26 | $36.00 | $82.26 |
| CEMENT MASON/CONCRETE FINISHER (ESSEX; MIDDLESEX; NORFOLK AND SUFFOLK COUNTY) | $49.19 | $40.86 | $90.05 |
| PLASTERER (MIDDLESEX; NORFOLK AND SUFFOLK COUNTIES) | $49.19 | $40.86 | $90.05 |
| PLUMBERS AND PIPEFITTERS (MIDDLESEX (ASHBY, AYER-WEST OF GREENVILLE BRANCH OF BOSTON AND MAINE RAILROAD, FT. DEVENS, GROTON, SHIRLEY, TOWNSEND)) | $55.00 | $31.57 | $86.57 |
| PLUMBER (ESSEX (AMES, ANDOVER, BEVERLY, BOXFORD, BYFIELD, DANVERS, ESSEX, GEORGETOWN, GLOUCESTER, GROVELAND, HAMILTON, HAVERHILL, IPSWICH, LAWRENCE, MANCHESTER, MARBLEHEAD, MERRIMAC, METHUEM, MIDDLETON, NEWBURY, NEWBURYPORT, NORTH ANDOVER, PEABODY, ROCKPORT, ROWLEY, SALEM, SALISBURY, TOPSFIELD, WENHAM, WEST NEWBURY)) | $69.84 | $36.43 | $106.27 |
| PLUMBER (ESSEX (LYNN, LYNNFIELD, NAHANT, SAUGUS, AND SWAMPSCOTT); MIDDLESEX (ACTON, ARLINGTON, ASHFORD, AYER-EXCEPT WEST OF GREENVILLE BRANCH OF BOSTON & MAINE RAIL ROAD, BEDFORD, BELMONT, BILLERICA, BOXBORO, BURLINGTON, CAMBRIDGE, CARLISE, CHELMSFORD, CONCORD, DRACUT, DUNSTABLE, EVERETT, FRAMINGHAM, HUDSON, HOLLIISTON, HOPKINTON, LEXINGTON, LINCOLN, LITTLETON, LOWELL, MALDEN, MARLBORO, MAYNARD, MEDFORD, MELROSE, NATICK, NEWTON, NORTH READING, PEPPERELL, READING, SHERBORN, SOMERVILLE, STON | $69.84 | $36.43 | $106.27 |
| PLUMBERS AND PIPEFITTERS (BARNSTABLE; BRISTOL; DUKES; NANTUCKET; AND NORFOLK (AVON, HOLBROOK, RANDOLPH, STOUGHTON) COUNTIES) | $52.49 | $33.60 | $86.09 |
| PIPEFITTER (ESSEX (AMES, ANDOVER, BEVERLY, BOXFORD, BYFIELD, DANVERS, ESSEX, GEORGETOWN, GLOUCESTER, GROVELAND, HAMILTON, HAVERHILL, IPSWICH, LAWRENCE, LYNN, LYNNFIELD, MANCHESTER, MARBLEHEAD, MERRIMAC, METHUEM, MIDDLETON, NAHANT, NEWBURY, NEWBURYPORT, NORTH ANDOVER, PEABODY, ROCKPORT, ROWLEY, SALEM, SALISBURY, SAUGUS, SWAMPSCOTT,TOPSFIELD, WENHAM, WEST NEWBURY); MIDDLESEX (ACTON, ARLINGTON, ASHFORD, AYER-EXCEPT WEST OF GREENVILLE BRANCH OF BOSTON & MAINE RAIL ROAD, BEDFORD, BELMONT, BILLER | $66.58 | $39.22 | $105.80 |
| ROOFERS: (ALL TEAR-OFF AND/OR REMOVAL OF ANY TYPES OF ROOFING AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL AREAS OF ANY TYPE WHERE A ROOF IS TO BE RELAID) | $53.53 | $35.69 | $89.22 |
| SPRINKLER FITTER (BRISTOL (PORTION WITHIN 35 MILE RADIUS FROM BOSTON CITY HALL; MIDDLESEX (EXCEPT ASHBY, TOWNSEND, AND PORTIONS OF PEPPERELL AND SHIRLEY BEYOND 35 MILE RADIUS FROM BOSTON CITY HALL); NORFOLK; PLYMOUTH (PORTION WITHIN 35 MILE RADIUS OF BOSTON CITY HALL); SUFFOLK) A. PAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN THE EMPLOYMENT OF A CONTRACTOR 20 WORKING DAYS PRIOR TO ANY SUCH PAID HOLIDAY | $72.05 | $40.76 | $112.81 |
| SPRINKLER FITTER (BRISTOL (SEEKONK, SWANSEA, AND SOMERSET)) A. PAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN THE EMPLOYMENT OF A CONTRACTOR 20 WORKING DAYS PRIOR TO ANY SUCH PAID HOLIDAY | $64.85 | $40.76 | $105.61 |
| SPRINKLER FITTER (BARNSTABLE; BRISTOL (BEYOND 35 MILE RADIUS OF BOSTON CITY HALL); DUKES; MIDDLESEX (ASHBY, TOWNSEND, PORTIONS OF PEPPERELL AND SHIRLEY BEYOND 35 MILE RADIUS OF BOSTON CITY HALL); NANTUCKET; PLYMOUTH (BEYOND 35 MILE RADIUS OF BOSTON CITY HALL)) | $53.25 | $29.75 | $83.00 |
| SHEET METAL WORKER (ESSEX; MIDDLESEX; NORFOLK; PLYMOUTH (EXCEPT EXCEPT MARION, MATTAPOISETT, ROCHESTER, WAREHAM); SUFFOLK) | $60.00 | $48.78 | $108.78 |
| SHEET METAL WORKER (BARNSTABLE; BRISTOL (ACUSHNET, ASSONET, DARTMOUTH, DIGHTON, FAIRHAVEN, FALL RIVER, FREETOWN, NEW BEDFORD, REHOBOTH, SEEEKONK, SOMERSET, SWANSEA, WESTPORT); DUKES; AND NANTUCKET) | $43.60 | $38.49 | $82.09 |
POWER EQUIPMENT OPERATORS 6 classifications · $58.72 to $91.53 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS: GROUP 6 OILER (ON TRUCK CRANES AND GRADALLS) STANT ENGINEER (ON TRUCK CRANE AND GRADALL) | $30.85 | $33.70 | $64.55 |
| POWER EQUIPMENT OPERATORS: GROUP 5 OILER (OTHER THAN TRUCK CRANES AND GRADALLS) | $25.02 | $33.70 | $58.72 |
| POWER EQUIPMENT OPERATORS: GROUP 4 ASSISTANT ENGINEER (FIREMAN) | $46.52 | $33.70 | $80.22 |
| POWER EQUIPMENT OPERATORS: GROUP 3 PUMPS (1-3 GROUPED); COMPRESSOR; WELDING MACHINE (1-3 GROUPED); GENERATOR; CONCRETE VIBRATOR; HEATER (POWER DRIVEN 1- 5); WELL POINT SYSTEM (OPERATING); SYPHON-PULSOMETER; CONCRETE MIXER; VALVES CONTROLLING PERMANENT PLANT AIR OR STEAM; CONVEYOR; JACKSON TYPE TAMPER; SINGLE DIAPHRAGM PUMP; LIGHTING PLANT | $37.02 | $33.70 | $70.72 |
| POWER EQUIPMENT OPERATORS: GROUP 2 SONIC OR VIBRATORY HAMMER; GRADER; SCRAPER; TANDEM SCRAPER; CONCRETE PUMP; BULLDOZER; TRACTOR; YORK RAKE; MULCHING MACHINE; PORTABLE STEAM BOILER; PORTABLE STEAM GENERATOR; ROLLER; SPREADER; TAMPER (SELF PROPELLED OR TRACTOR DRAWN); ASPHALT PAVER; MECHANIC - MAINTENANCE; PAVING SCREED MACHINE; STATIONARY STEAM BOILER; PAVING CONCRETE FINISHING MACHINE; CAL TRUCK; BALLAST REGULATOR; SWITCH TAMPER; RAIL ANCHOR MACHINE; TIRE TRUCK | $57.18 | $33.70 | $90.88 |
| POWER EQUIPMENT OPERATORS: GROUP 1 CRANE; SHOVEL; TRUCK CRANE; CHERRY PICKER; DRAGLINE; TRENCH HOE; BACKHOE; THREE DRUM MACHINE; DERRICK; PILE DRIVER; ELEVATOR TOWER; HOIST; GRADALL; SHOVEL DOZER; FRONT END LOADER; FORK LIFT; SUGER; BORING MACHINE; ROTARYU DRILL; POST HOLE HAMMER; POST HOLE DIGGER; PUMPCRETE MACHINE; ASPHALT PLANT (ON SITE); CONCRETE BATCHING AND/OR MIXING PLANT (ON SITE); CRUSHER PLANT (ON SITE); PAVING CONCRETE MIXER; TIMBER JACK | $57.83 | $33.70 | $91.53 |
LABORERS 25 classifications · $56.71 to $76.95 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS:, HEAVY CONSTRUCTION: GROUP 6 ASBESTOS ABATEMENT; TOXIC AND HAZARDOUS WASTE LABORERS | $40.95 | $29.70 | $70.65 |
| LABORERS:, HEAVY CONSTRUCTION: GROUP 5 FLAGGER | $39.70 | $29.70 | $69.40 |
| LABORERS:, HEAVY CONSTRUCTION: GROUP 4 BLASTER; POWDERMAN | $39.95 | $29.70 | $69.65 |
| LABORERS:, HEAVY CONSTRUCTION: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF POWERED DRILLS | $39.70 | $29.70 | $69.40 |
| LABORERS:, HEAVY CONSTRUCTION: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENDER; PIPELAYER; PNEUMATIC DRILL OPERATOR; PNEUMATIC TOOL OPERATOR; WAGON DRILL OPERATOR, JACK HAMMER OPERATOR, PAVEMENT BREAKER, CARBIDE CORE DRILLING MACHINE, CHAIN SAW OPERATOR, BARCO TYPE JUMPING TAMPERS, CONCRETE PUMP, MOTORIZED MORTAR MIXER, RIDE-ON-MOTORIZED BUGGY | $39.20 | $29.70 | $68.90 |
| LABORERS:, HEAVY CONSTRUCTION: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS | $38.95 | $29.70 | $68.65 |
| LABORERS: GROUP 7 - FLAGGERS (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $27.01 | $29.70 | $56.71 |
| LABORERS: GROUP 6- ASBESTOS REMOVAL LABORERS/HAZ-MAT LABORERS (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 5- PRE-CAST FLOOR AND ROOF PLANK ERECTOR (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 4- BLASTER; POWDERMAN (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 3- AIR TRACK, BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 2 - JACKHAMMER OPERATOR; PAVEMENT BREAKER; ASPHALT RAKER CARBIDE CORE DRILLING MACHINE; CHAIN SAW OPERATOR; PIPELAYER; BARCO TYPE JUMPING TAMPERS; LASER BEAM; CONCRETE PUMP; MASON TENDER; MOTORIZED MORTAR MIXER; RIDE-ON MOTORIZED BUGGY; FENCE AND BEAM RAIL ERECTOR2 (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 1- LABORERS; CARPENTER TENDERS (SUFFOLK COUNTY (BOSTON, CHELSEA, REVERE, WINTHROP, DEER & NUT ISLANDS); MIDDLESEX COUNTY (ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKEFIELD, WINCHESTER, WINTHROP, AND WOBURN ONLY); NORFOLK COUNTY (BROOKLINE, DEDHAM, AND MILTON ONLY)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 6- ASBESTOS REMOVAL LABORERS/HAZ-MAT LABORERS (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE, DEDHAM AND MILTON)) | $46.10 | $29.70 | $75.80 |
| LABORERS: GROUP 5- PRE-CAST FLOOR AND ROOF PLANK ERECTOR (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE, DEDHAM AND MILTON)) | $38.95 | $29.70 | $68.65 |
| LABORERS: GROUP 4- BLASTER; POWDERMAN (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE, DEDHAM AND MILTON)) | $38.95 | $29.70 | $68.65 |
| LABORERS: GROUP 3- AIR TRACK, BLOCK PAVER; HAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE, DEDHAM AND MILTON)) | $38.95 | $29.70 | $68.65 |
| LABORERS: GROUP 2- JACKHAMMER OPERATOR; PAVEMENT BREAKER; ASPHALT RAKER CARBIDE CORE DRILLING MACHINE; CHAIN SAW OPERATOR; PIPELAYER; BARCO TYPE JUMPING TAMPERS; LASER BEAM; CONCRETE PUMP; MASON TENDER; MOTORIZED MORTAR MIXER; RIDE-ON MOTORIZED BUGGY; FENCE AND BEAM RAIL ERECTOR (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE, DEDHAM AND MILTON)) | $38.95 | $29.70 | $68.65 |
| LABORERS: GROUP 1- LABORERS; CARPENTER TENDERS (COUNTIES OF BARNSTABLE; BRISTOL; DUKES; ESSEX; NANTUCKET; MIDDLESEX (WITH THE EXCEPTION OF ARLINGTON, BELMONT, BURLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, READING, SOMERVILLE, STONEHAM, WAKFIELD, WINCHESTER, WINTHROP AND WOBURN); NORFOLK (WITH THE EXCEPTION OF BROOKLINE, DEDHAM AND MILTON)) | $38.95 | $29.70 | $68.65 |
| LABORERS:, WRECKING: GROUP 6 ASBESTOS, LEAD PAINT, TOXIC AND HAZARDOUS WASTE. (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET NORFOLK AND SUFFOLK COUNTIES) | $46.25 | $29.70 | $75.95 |
| LABORERS:, WRECKING: GROUP 5 YARDMAN, BURNERS, SAWYERS. (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET NORFOLK AND SUFFOLK COUNTIES) | $45.35 | $29.70 | $75.05 |
| LABORERS:, WRECKING: GROUP 4 YARDMAN (SALVAGE YARD ONLY). (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET NORFOLK AND SUFFOLK COUNTIES) | $42.25 | $29.70 | $71.95 |
| LABORERS:, WRECKING: GROUP 3 SMALL BACKHOES, LOADERS ON TRACKS, BOBCAT TYPE LOADERS, HYDRAULIC "BROCK" TYPE HAMMER OPERATORS, CONCRETE CUTTING SAWS. (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET NORFOLK AND SUFFOLK COUNTIES) | $47.25 | $29.70 | $76.95 |
| LABORERS:, WRECKING: GROUP 2 BURNERS, JACKHAMMERS. (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET NORFOLK AND SUFFOLK COUNTIES) | $47.00 | $29.70 | $76.70 |
| LABORERS:, WRECKING: GROUP 1 ADZEMAN, WRECKING LABORER. (BARNSTABLE, BRISTOL, DUKES, ESSEX, MIDDLESEX, NANTUCKET NORFOLK AND SUFFOLK COUNTIES) | $46.25 | $29.70 | $75.95 |
TRUCK DRIVERS 7 classifications · $78.13 to $79.17 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT (DOUBLE HOOKUP) POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.82 | $37.35 | $79.17 |
| TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.53 | $37.35 | $78.88 |
| TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTORATION EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.24 | $37.35 | $78.59 |
| TRUCK DRIVERS: GROUP 4 FOUR AND FIVE AXLE EQUIPMENT WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.14 | $37.35 | $78.49 |
| TRUCK DRIVERS: GROUP 3 THREE AXLE EQUIPMENT AND TIREMAN POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.02 | $37.35 | $78.37 |
| TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $40.95 | $37.35 | $78.30 |
| TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $40.78 | $37.35 | $78.13 |
Heavy MA20260006 rev 2
DREDGING 7 classifications · $45.01 to $63.82 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| DREDGING: CLASS D: OILER, DECKHAND, SHOREMAN, RODMAN, SCOWMAN, COOK, MESSMAN, PORTER/JANITOR. (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $30.86 | $14.15 | $45.01 |
| DREDGING: CLASS C2: BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $37.15 | $14.57 | $51.72 |
| DREDGING: CLASS C1: MATE, DRAG BARGE OPERATOR, ASSISTANT FILL PLACER, WELDER, STEWARD. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $38.38 | $14.66 | $53.04 |
| DREDGING: CLASS B2: CERTIFIED WELDER. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $39.46 | $14.73 | $54.19 |
| DREDGING: CLASS B1: DERRICK OPERATOR (180 SWING), SPIDER/SPILL BARGE OPERATOR, ENGINEER, ELECTRICIAN, CHIEF WELDER, CHIEF MATE, FILL PLACER, OPERATOR II, MAINTENANCE ENGINEER, LICENSED BOAT OPERATOR, LICENSED CREW BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $41.93 | $14.90 | $56.83 |
| DREDGING: CLASS A2: CRANE OPERATOR (360 SWING) INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $43.20 | $14.99 | $58.19 |
| DREDGING: CLASS A1: DECK CAPTAIN; MECHANICAL DREDGE OPERATOR, LEVERMAN, LICENSED TUG OPERATOR OVER 1000 HP. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | $48.48 | $15.34 | $63.82 |
Highway MA20260024 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (INCLUDES TRAFFIC SIGNALIZATION) | $66.17 | $37.08 | $103.25 |
| POWER EQUIPMENT OPERATOR GROUP 2 BULLDOZER; GRADER/BLADE; MILLING MACHINE; ROLLER | $57.18 | $33.70 | $90.88 |
| POWER EQUIPMENT OPERATOR GROUP 1 BACKHOE/EXCAVATOR/TRACKHOE; BROOM/SWEEPER; CRANE; GRADALL; LOADER; PAVER (ASPHALT, AGGREGATE, AND CONCRETE); POST DRIVER (GUARDRAIL/FENCES) | $57.83 | $33.70 | $91.53 |
| IRONWORKER: ORNAMENTAL AND STRUCTURAL | $57.87 | $37.67 | $95.54 |
| LABORER (LANDSCAPE) | $46.20 | $29.70 | $75.90 |
| LABORER (GUARDRAIL INSTALLATION) | $46.20 | $29.70 | $75.90 |
| PAINTER: STEEL | $56.76 | $36.00 | $92.76 |
| TRUCK DRIVER: FLATBED TRUCK | $48.53 | $0.00 | $48.53 |
| TRUCK DRIVER: DUMP TRUCK | $37.74 | $11.86 | $49.60 |
| TRUCK DRIVER: CONCRETE TRUCK | $33.69 | $15.79 | $49.48 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $53.35 | $12.78 | $66.13 |
| TRAFFIC CONTROL: FLAGGER | $23.00 | $20.44 | $43.44 |
| PAINTER: SPRAY (LINESTRIPING) | $47.30 | $6.42 | $53.72 |
| OPERATOR: PILEDRIVER | $42.56 | $17.34 | $59.90 |
| OPERATOR: MECHANIC | $48.74 | $11.79 | $60.53 |
| OPERATOR: FORKLIFT | $64.67 | $0.00 | $64.67 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $64.67 | $15.70 | $80.37 |
| IRONWORKER, REINFORCING | $57.39 | $19.17 | $76.56 |
| CEMENT MASON/CONCRETE FINISHER | $56.70 | $21.08 | $77.78 |
| CARPENTER, INCLUDES FORM WORK | $66.59 | $15.41 | $82.00 |
LABORER 6 classifications · $50.97 to $76.05 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| LABORER: FENCE ERECTION | $46.20 | $29.70 | $75.90 |
| LABORER: CONCRETE SURFACER | $46.20 | $29.85 | $76.05 |
| LABORER: JACK HAMMER | $38.69 | $17.33 | $56.02 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | $44.43 | $14.18 | $58.61 |
| LABORER: COMMON OR GENERAL | $44.97 | $16.07 | $61.04 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $33.65 | $17.32 | $50.97 |
Residential MA20260004 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER, PLASTERER, STONEMASON (LOWELL CHAPTER MIDDLESEX COUNTY (ACTON, ASBY, ASHLAND, AYER, BEDFORD, BILLERICA, BOXBORO, CARLISLE, CHEMSFORD, DRACUT, DUNSTABLE, FRAMINGHAM, FT. DEVENS, GROTON, HOLLISTON, HOPKINTON, HUDSON, LITTLETON, LOWELL, MAYNARD, NATICK, NORTH ACTON, PEPPERELL, SHERBORN, SHIRLEY, SOUTH ACTON, STOW, TEWKSBURY, TOWNSEND, TYNGSBORO, WEST ACTON, WESTFORD, WILMINGTON) NORFOLK (MEDFIELD, MEDWAY, MILLS) WORCESTER (ASHBUMHAM, ATHOL, FITCHBURG, GARDNER, HARVARD, HOPEDALE, HUBBAR | $62.40 | $34.40 | $96.80 |
| BRICKLAYER, PLASTERERS, STONEMASONS, TILE LAYERS (SPRINGFIELD/PITTSFIELD CHAPTER BERKSHIRE, HAMPDEN, HAMPSHIRE, WORCESTER (WARREN) COUNTIES) | $50.81 | $32.27 | $83.08 |
| BRICKLAYER (FOXBORO CHAPTER BRISTOL (ATTLEBORO, BERKLEY, DIGHTON, MANSFIELD, NORTH ATTLEBORO, NORTON, RAYNHAM, REHOBOTH, SEEKONK, TAUNTON) NORFOLK (BELLINGHAM, CANTON, DEDHAM, FOXBORO, FRANKLIN, NORFOLK, NORWOOD, PLAINVILLE, SHARON, WALPOLE, WESTWOOD, WRENHTHAM) PLYMOUTH (LAKEVILLE)) | $62.40 | $34.40 | $96.80 |
| BRICKLAYER, PLASTERER, STONEMASON (WORCESTER CHAPTER (AUBURN, BARRE, BLACKSTONE, BERLIN, BOLTON, BOYLSTON, BROOKFIELD, CHARLTON, CLINTON, DOUGLAS, DUDLEY, GRAFTON, HARDWICK, HOLDEN, LEICESTER, MENDON, MILLBURY, MILLVILLE, NEW BRAINTREE, NORTHBORO, NORTHBRIDGE, OAKHAM, OXFORD, PAXTON, RUTLAND, SHREWBURY, SOUTHBRIDGE, SPENCER, STURBRIDGE, SUTTON, UPTON, UXBRIDGE, WEBSTER, WESTBORO, WEST BOYLSTON, WORCESTER)) | $60.26 | $33.71 | $93.97 |
| BRICKLAYER (BOSTON CHAPTER MIDDLESEX (ARLINGTON, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, MELROSE, SOMERVILLE) NORFOLK (BROOKLINE, MILTON) SUFFOLK) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, PLASTERER (LYNN CHAPTER ESSEX (AMESBURY, ANDOVER, BEVERLY, BOXFORD, DANVERS, ESSEX, GEORGETOWN, GLOUCESTER, GROVELAND, HAMILTON, HAVERHILL, IPSEWICH, LAWRENCE, LYNN, LYNNFIELD, MANCHESTER, NAHANT, NEWBURY, NEWBURYPORT, NORTH ANDOVER, PEABODY, ROCKPORT, ROWLEY, SALISBURY, SALEM, SAUGUS, SWAMPSCOTT, TOPSFIELD, WAKEFIELD, WENHAM, WEST NEWBURY) MIDDLESEX (READING, NORTH READING, WAKEFIELD)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, PLASTERER (NEWTON CHAPTER MIDDLESEX (NEWTON); NORFOLK (DOVER, NEEDHAM, WELLESLEY)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER (NEW BEDFORD CHAPTER BARNSTABLE, BRISTOL (ACUSHNET, DARMOUTH, FAIRHAVE, FALL RIVER, FREETOWN, NEW BEDFORD, SOMERSET, SWANSEA, WESTPORT) PLYMOUTH (MARION, MATTAPOISETT, ROCHESTER, WAREHAM)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, PLASTERER (QUINCY CHAPTER NORFOLK (AVON, BRAINTREE, COHASSET, HOLBROOK, QUINCY, RANDOLPH, STOUGHTON, WEYMOUTH) PLYMOUTH (ABINGTON, BRIDGEWATER, BROCKTON, CARVER, DUXBURY, EAST BRIDGEWATER, HALIFAX, HANOVER, HANSON, HINGHAM, HULL, KINGSTON, MARSHFIELD, MIDDLEBORO, NORWELL, PEMBROKE, PLYMOUTH, ROCKLAND, SCITUATE, WEST BRIDGEWATER, WHITMAN)) | $64.50 | $37.54 | $102.04 |
| BRICKLAYER, PLASTERER (WALTHAM CHAPTER MIDDLESEX (BELMONT, BURLINGTON, CONCORD, LIXINGTON, LINCOLN, STONEHAM, SUDBURY, WALTHAM, WATERTOWN, WAYLAND, WESTON, WINCHESTER, WOBURN)) | $64.50 | $37.54 | $102.04 |
| TILE LAYER (BARNSTABLE, BRISTOL, SUFFOLK AND WORCESTER) | $64.50 | $37.54 | $102.04 |
| CARPENTERS (INCLUDING DRYWALL HANGING & ACOUSTICAL CEILING INSTALLATION) (MIDDLESEX (BELMONT, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, SOMERVILLE) NORFOLK (BROOKLINE, DEDHAM, MILTON) AND SUFFOLK) | $61.19 | $31.55 | $92.74 |
| CARPENTERS (INCLUDING DRYWALL HANGING & ACOUSTICAL CEILING INSTALLATION) (WORCESTER COUNTY (EXCEPT GILBERTVILLE, HARDWICK, WARREN, WEST BROOKFIELD)) | $50.10 | $31.45 | $81.55 |
| CARPENTERS (INCLUDING DRYWALL HANGING & ACOUSTICAL CEILING INSTALLATION) (BERKSHIRE, HAMPDEN, HAMPSHIRE AND WORCESTER (GILBERTVILLE, HARDWICK, WARREN, WEST BROOKFIELD)) | $43.33 | $27.82 | $71.15 |
| CARPENTERS (INCLUDING DRYWALL HANGING & ACOUSTICAL CEILING INSTALLATION) (BRISTOL (ATTLEBOROUGH, NORTH ATTLEBOROUGH) ESSEX, MIDDLESEX (EXCEPT BELMONT, CAMBRIDGE, EVERETT, MALDEN, MEDFORD, SOMERVILLE) NORFOLK (BELLINGHAM, CANTON, FOXBORO, FRANKLIN, MEDFIELD, MEDWAY, MILLIS, NEEDHAM, NORFOLK, NORWOOD, PLAINVILLE, QUINCY, SHARON, WALPOLE, WELLESLEY, WESTWOOD, WRENTHAM) AND PLYMOUTH (DUXBURY, HANOVER, HINGHAM, HULL, MARSHFIELD, NORWELL, PEMBROKE, ROCKLAND AND SCITUATE)) | $50.10 | $31.45 | $81.55 |
| CARPENTERS (INCLUDING DRYWALL HANGING & ACOUSTICAL CEILING INSTALLATION) (BARNSTABLE, BRISTOL (EXCEPT ATTLEBORO AND NORTH ATTLEBORO) AND PLYMOUTH (BRIDGEWATER, BROCKTON, KINGSTON, LAKEVILLE, MIDDLEBORO, PLYMOUTH, SOUTH HANOVER, WHITMAN)) | $39.28 | $27.90 | $67.18 |
| CARPENTER, NEW WOOD FRAME CONSTRUCTION NOT EXCEEDING 4 STORIES INCLUDING BASEMENT: WOOD FRAMING, SIDING AND EXTERIOR TRIM WORK (ZONE 2: BARNSTABLE, BERKSHIRE, BRISTOL, ESSEX, HAMPDEN, HAMPSHIRE, PLYMOUTH, WORCESTER COUNTIES AND PART OF MIDDLESEX, NORFOLK AND SUFFOLK COUNTIES (ALL OTHER CITIES AND TOWNS IN MASSACHUSETTS + CHELSEA & WINTHROP)) | $26.55 | $13.02 | $39.57 |
| CARPENTER, NEW WOOD FRAME CONSTRUCTION NOT EXCEEDING 4 STORIES INCLUDING BASEMENT: ALL OTHER CARPENTRY WORK ON WOOD FRAME PROJECTS (ZONE 2: BARNSTABLE, BERKSHIRE, BRISTOL, ESSEX, HAMPDEN, HAMPSHIRE, PLYMOUTH, WORCESTER COUNTIES AND PART OF MIDDLESEX, NORFOLK AND SUFFOLK COUNTIES (ALL OTHER CITIES AND TOWNS IN MASSACHUSETTS + CHELSEA & WINTHROP)) | $26.55 | $13.02 | $39.57 |
| CARPENTERS, NEW WOOD FRAME CONSTRUCTION NOT EXCEEDING 4 STORIES INCLUDING BASEMENT: WOOD FRAMING, SIDING AND EXTERIOR TRIM WORK (ZONE 1: MIDDLESEX, NORFOLK AND SUFFOLK COUNTIES (CONSISTS OF BOSTON, ISLANDS OF BOSTON HARBOR, BROOKLINE, CAMBRIDGE, DEDHAM, MALDEN, MEDFORD AND SOMERVILLE)) | $31.61 | $14.02 | $45.63 |
| CARPENTERS, NEW WOOD FRAME CONSTRUCTION NOT EXCEEDING 4 STORIES INCLUDING BASEMENT: ALL OTHER CARPENTRY WORK ON WOOD FRAME PROJECTS (ZONE 1: MIDDLESEX, NORFOLK AND SUFFOLK COUNTIES (CONSISTS OF BOSTON, ISLANDS OF BOSTON HARBOR, BROOKLINE, CAMBRIDGE, DEDHAM, MALDEN, MEDFORD AND SOMERVILLE)) | $31.61 | $14.02 | $45.63 |
| ELECTRICIAN (HAMPDEN (EXCEPT CHESTER AND HOLYOKE); HAMPSHIRE (BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 |
| TELEDATA SYSTEM INSTALLER: BERKSHIRE COUNTY | $52.16 | $29.56 | $81.72 |
| ELECTRICIAN (BERKSHIRE; HAMPDEN (CHESTER, HOLYOKE); HAMPSHIRE (EXCEPT BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 |
| TELEDATA SYSTEM INSTALLER (MIDDLESEX (ASHBY, ASHLAND, AYER, FT. DEVENS, GROTON, HOPKINTON, HUDSON, MARLBORO, PEPPERELL, SHIRLEY, STOW, TOWNSEND); WORCESTER (EXCEPT WARREN)) | $36.12 | $34.51 | $70.63 |
| ELECTRICIAN (MIDDLESEX (ASHBY, ASHLAND, AYER, FT. DEVENS, GROTON, HOPKINTON, HUDSON, MARLBORO, PEPPERELL, SHIRLEY, STOW, TOWNSEND); WORCESTER (EXCEPT WARREN)) | $48.16 | $36.20 | $84.36 |
| ELECTRICIAN (WORCESTER (WARREN)) | $48.16 | $36.20 | $84.36 |
| ELECTRICIAN (BRISTOL (NORTH & SOUTH ATTLEBORO, SEEKONK)) | $56.11 | $24.74 | $80.85 |
| ELECTRICIAN (ESSEX (AMESBURY, ANDOVER, BOXFORD, GEORGETOWN, GROVELAND, HAVERHILL, LAWRENCE, MERRIMAC, METHUEN, NEWBURY, NEWBURYPORT, NORTH ANDOVER, ROWLEY, SALISBURY, WEST NEWBURY); MIDDLESEX (BEDFORD, BILLERICA, BOXBORO, BURLINGTON, CARLISLE, CHELMSFORD, DRACUT, DUNSTABLE LITTLETON, LOWELL, NORTH READING, TEWKSBURY, TYNGSBORO, WESTFORD, WILMINGTON)) | $66.17 | $37.08 | $103.25 |
| ELECTRICIAN (ESSEX (BEVERLY, DANVERS, ESSEX, GLOUCESTER, HAMILTON, IPSWICH, MANCHESTER, MARBLEHEAD, MIDDLETON, PEABODY, ROCKPORT, SALEM, TOPSFIELD, WENHAM)) | $66.17 | $37.08 | $103.25 |
| TELEDATA SYSTEM INSTALLER: ESSEX; MIDDLESEX {EXCLUDING ASHBY, ASHLAND, AYER, FT. DEVENS, GROTON, HOKINTON, HUDSON, MARLBORO, PEPPERELL, SHIRLEY, STOW, TOWNSEND}; NORFOLK {EXCLUDING AVON, HOLBROOK, PLAINVILLE, RANDOLPH, STOUGHTON}; SUFFOLK (ESSEX (LYNN, LYNNFIELD, NAHANT, SAUGUS, SWAMPSCOTT); MIDDLESEX (ACTON, ARLINGTON, BELMONT, CAMBRIDGE, CONCORD, EVERETT, FRAMINGHAM, HOLLISTON, LEXINGTON, LINCOLN, MALDEN, MAYNARD, MEDFORD, MELROSE, NATICK, NEWTON, READING, SHERBORN, SOMERVILLE, STONEHAM, SUD | $52.94 | $34.74 | $87.68 |
| ELECTRICIAN (ESSEX (LYNN, LYNNFIELD, NAHANT, SAUGUS, SWAMPSCOTT); MIDDLESEX (ACTON, ARLINGTON, BELMONT, CAMBRIDGE, CONCORD, EVERETT, FRAMINGHAM, HOLLISTON, LEXINGTON, LINCOLN, MALDEN, MAYNARD, MEDFORD, MELROSE, NATICK, NEWTON, READING, SHERBORN, SOMERVILLE, STONEHAM, SUDBURY, WAKEFIELD, WALTHAM, WATERTOWN, WAYLAND, WESTON, WINCHESTER, WOBURN); NORFOLK (BELLINGHAM, BRAINTREE, BROOKLINE, CANTON, COAHASSET, DEDHAM, DOVER, FOXBORO, FRANKLIN, MEDFIELD, MEDWAY, MILLIS, MILTON, NEEDHAM, NORFOLK, NORW | $66.17 | $37.08 | $103.25 |
| TELEDATA SYSTEM INSTALLER: PLYMOUTH COUNTY (EXCEPT TOWNSHIPS OF HINGHAM AND HULL) | $42.52 | $28.47 | $70.99 |
| ELECTRICIAN (BARNSTABLE, BRISTOL (EXCEPT ATTLEBORO, NORTH ATTLEBORO, SEEKONK); NORFOLK (AVON, HALBROOK, RANDOLPH, SLOUGHTON); PLYMOUTH (EXCEPT HINGHAM AND HULL TOWNSHIPS)) | $50.02 | $31.05 | $81.07 |
| ELEVATOR MECHANIC (BARNSTABLE, BRISTOL, ESSEX, MIDDLESEX, NORFOLK AND SUFFOLK) | $74.17 | $38.44 | $112.61 |
| ELEVATOR MECHANIC (BERKSHIRE, HAMPDEN AND HAMPSHIRE) | $66.41 | $38.44 | $104.85 |
| POWER EQUIPMENT OPERATOR: EXCAVATORS & LOADERS (BARNSTABLE; BRISTOL; ESSEX; MIDDLESEX, NORFOLK; PLYMOUTH; SUFFOLK; AND WORCESTER (REMAINDER OF COUNTY)) | $57.18 | $33.70 | $90.88 |
| POWER EQUIPMENT OPERATOR: EXCAVATORS & LOADERS (WORCESTER (ATHOL, BARRE, BROOKFIELD, EAST BROOKFIELD, HARDWICK, NEW BRAINTREE, NORTH BROOKFIELD, OAKHAM, PETERSHAM, PHLLIPSTON, ROYALSTON, STRUTHBRIDGE, TEMPLETON, WARREN, WEST BROOKFIELD, WINCHENDON)) | $57.18 | $33.70 | $90.88 |
| POWER EQUIPMENT OPERATOR: EXCAVATORS & LOADERS (BERKSHIRE; HAMPDEN AND HAMPSHIRE COUNTIES) | $41.23 | $30.58 | $71.81 |
| LABORERS: MASON TENDER, STONE/STUCCO (BERKSHIRE, HAMPSHIRE (CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD AND WORTHINGTON)) | $31.54 | $25.63 | $57.17 |
| LABORERS: MASON TENDER, STONE/STUCCO (HAMPDEN, HAMPSHIRE (EXCEPT CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD AND WORTHINGTON)) | $32.75 | $26.02 | $58.77 |
| PAINTER: DRYWALL FINISHING ONLY (BERKSHIRE, HAMPDEN, AND HAMPSHIRE COUNTIES) | $32.33 | $26.35 | $58.68 |
| PAINTER: DRYWALL FINISHING ONLY (BARNSTABLE, BRISTOL, ESSEX, MIDDLESEX, NORFOLK, PLYMOUTH, SUFFOLK, AND WORCESTER COUNTIES) | $39.86 | $30.25 | $70.11 |
| PLASTERER (MIDDLESEX; NORFOLK AND SUFFOLK COUNTIES) | $43.97 | $33.87 | $77.84 |
| PLUMBERS, PIPEFITTERS (INCLUDING HVAC WORK) (MIDDLESEX (ASHBY, AYER-WEST OF GREENVILLE BRANCH OF BOSTON AND MAINE RAILROAD, FT. DEVENS, GROTON, SHIRLEY, TOWNSEND) WORCESTER (EXCEPT HOPEDALE AND SOUTHBORO)) | $55.00 | $31.57 | $86.57 |
| PLUMBER (ESSEX(AMES, ANDOVER, BEVERLY, BOXFORD, BYFIELD, DANVERS, ESSEX, GEORGETOWN, GLOUCESTER, GROVELAND, HAMILTON, HAVERHILL, IPSWICH, LAWRENCE,MANCHESTER, MARBLEHEAD, MERRIMAC, METHUEM, MIDDLETON, NEWBURY, NEWBURYPORT, NORTH ANDOVER, PEABODY, ROCKPORT, ROWLEY, SALEM, SALISBURY, TOPSFIEILD, WENHAM, WEST NEWBURY)) | $69.84 | $36.43 | $106.27 |
| PLUMBER (ESSEX(LYNN, LYNNFIELD, NAHANT, SAUGUS, AND SWAMPSCOTT); MIDDLESEX (ACTON, ARLINGTON, ASHLAND, AYER-EXCEPT WEST OF GREENVILLE BRANCH OF BOSTON & MAINE RAIL ROAD, BEDFORD, BELMONT, BILLERICA, BOXBORO, BURLINGTON, CAMBRIDGE, CARLISLE, CHELMSFORD, CONCORD, DRACUT, DUNSTABLE, EVERETT, FRAMINGHAM, HUDSON, HOLLISTON, HOPKINTON, LEXINGTON, LINCOLN, LITTLETON, LOWELL, MALDEN, MARLBORO, MAYNARD, MEDFORD, MELROSE, NATICK, NEWTON, NORTH READING, PEPPERELL, READING, SHERBORN, SOMERVILLE, STONE | $69.84 | $36.43 | $106.27 |
| PLUMBERS, PIPEFITTERS (INCLUDING HVAC WORK) (BARNSABLE; BRISTOL; PLYMOUTH (EXCEPT HINGHAM, HULL, SCITUATE)) | $52.49 | $33.60 | $86.09 |
| PLUMBERS, PIPEFITTERS (INCLUDING HVAC WORK) (BERKSHIRE (BECKET, OTIS, SANDISFIELD); HAMPDEN; HAMPSHIRE) | $52.26 | $31.05 | $83.31 |
| PLUMBERS, PIPEFITTERS (INCLUDING HVAC WORK) (BERKSHIRE (EXCEPT BECKET, OTIS, SANDISFIELD)) | $52.26 | $31.05 | $83.31 |
| PIPEFITTER INCLUDING HVAC WORK (ESSEX (AMES, ANDOVER, BEVERLY, BOXFORD, BYFIELD, DANVERS, ESSEX, GEORGETOWN, GLOUCESTER, GROVELAND, HAMILTON, HAVERHILL, IPSWICH, LAWRENCE, LYNN, LYNNFIELD, MANCHESTER, MARBLEHEAD, MERRIMAC, METHUEM, MIDDLETON, NAHANT, NEWBURY, NEWBURYPORT, NORTH ANDOVER, PEABODY, ROCKPORT, ROWLEY, SALEM, SALISBURY, SAUGUS, SWAMPSCOTT,TOPSFIELD, WENHAM, WEST NEWBURY); MIDDLESEX (ACTON, ARLINGTON, ASHFORD, AYER-EXCEPT WEST OF GREENVILLE BRANCH OF BOSTON & MAINE RAIL ROAD, BEDF | $66.58 | $39.22 | $105.80 |
| ROOFER, WATERPROOFERS/CAULKERS (BARNSTABLE, BRISTOL, ESSEX, MIDDLESEX, NORFOLK, SUFFOLK, WORCESTER) | $53.53 | $35.69 | $89.22 |
| ROOFER: SLATE & TILE ROOF (BERKSHIRE, HAMPDEN, HAMPSHIRE) | $42.48 | $30.14 | $72.62 |
| ROOFER, WATERPROOFERS/CAULKERS (BERKSHIRE, HAMPDEN, HAMPSHIRE) | $42.48 | $30.14 | $72.62 |
| SHEET METAL WORKER (WORCESTER (HARVARD, LANCASTER)) | $60.00 | $48.78 | $108.78 |
| SHEET METAL WORKER (BARNSTABLE, BRISTOL (ACUSHNET, DARTMOUTH, DIGHTON, FAIRHAVEN, FALL RIVER, FREETOWN, NEW BEDFORD, REHOBOTH, SEEKONK, SOMERSET, SWANSEA, WESTPORT); DUKES, AND NANTUCKET) | $43.60 | $38.49 | $82.09 |
| SHEET METAL WORKER (ESSEX; MIDDLESEX; NORFOLK; PLYMOUTH (EXCEPT MARION MATTAPOISETT, ROCHESTER, WAREHAM); SUFFOLK) | $60.00 | $48.78 | $108.78 |
| SHEET METAL WORKER (WORCESTER (EXCEPT HARVARD & LANCASTER)) | $43.48 | $36.46 | $79.94 |
| SHEET METAL WORKER (BERKSHIRE, HAMPDEN AND HAMPSHIRE COUNTIES) | $43.48 | $36.46 | $79.94 |
| PAINTER (BRUSH & ROLLER, EXCLUDING DRYWALL FINISHING) | $30.86 | $0.00 | $30.86 |
| LABORER (UNSKILLED) | $18.73 | $6.33 | $25.06 |
| FLOOR LAYER: CARPET | $31.96 | $0.00 | $31.96 |
| CEMENT MASON/CONCRETE FINISHER | $39.38 | $0.00 | $39.38 |