Marion County, Alabama: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Building AL20260081 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $34.21 | $23.92 | $58.13 |
| CARPENTER | $30.26 | $14.78 | $45.04 |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $29.90 | $14.55 | $44.45 |
| PLUMBER | $35.20 | $13.51 | $48.71 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $33.78 | $22.03 | $55.81 |
| TRUCK DRIVER: DUMP TRUCK | $14.05 | $0.00 | $14.05 |
| PAINTER (BRUSH AND ROLLER) | $15.10 | $0.00 | $15.10 |
| OPERATOR: BULLDOZER | $15.72 | $2.64 | $18.36 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.48 | $11.78 | $32.26 |
| LABORER: COMMON OR GENERAL | $13.75 | $0.00 | $13.75 |
| HVAC MECHANIC (HVAC DUCT INSTALLATION ONLY) | $20.50 | $2.12 | $22.62 |
| ELECTRICIAN | $21.59 | $6.39 | $27.98 |
| CEMENT MASON/CONCRETE FINISHER | $16.50 | $1.12 | $17.62 |
| BRICKLAYER | $20.00 | $0.00 | $20.00 |
Heavy AL20260001 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| SELF-PROPELLED HOPPER DREDGE DRAG TENDERS THE FOLLOWING RATES WERE REVISED PURSUANT TO 29 CFR 1.6(C)(1) ON 02/07/2025 | $20.36 | $7.24 | $27.60 |
Highway AL20260137 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: WATER TRUCK | $12.95 | $0.00 | $12.95 |
| TRUCK DRIVER: LOWBOY TRUCK | $15.88 | $0.00 | $15.88 |
| TRUCK DRIVER: FLATBED TRUCK | $15.72 | $0.00 | $15.72 |
| TRUCK DRIVER: DUMP TRUCK | $12.99 | $0.00 | $12.99 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $12.76 | $0.00 | $12.76 |
| TRAFFIC CONTROL: FLAGGER | $13.24 | $0.00 | $13.24 |
| OPERATOR: ROLLER | $14.50 | $0.00 | $14.50 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $16.39 | $0.00 | $16.39 |
| OPERATOR: MILLING MACHINE | $12.72 | $0.00 | $12.72 |
| OPERATOR: MECHANIC | $17.65 | $0.00 | $17.65 |
| OPERATOR: LOADER | $15.04 | $0.00 | $15.04 |
| OPERATOR: GRADER/BLADE | $17.85 | $0.00 | $17.85 |
| OPERATOR: DISTRIBUTOR | $16.10 | $0.00 | $16.10 |
| OPERATOR: CRANE | $24.98 | $0.00 | $24.98 |
| OPERATOR: BULLDOZER | $15.64 | $0.00 | $15.64 |
| OPERATOR: BROOM/SWEEPER | $12.52 | $0.00 | $12.52 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $15.97 | $0.00 | $15.97 |
| OPERATOR: ASPHALT SPREADER | $14.31 | $0.00 | $14.31 |
| LABORER: EROSION CONTROL | $12.35 | $0.00 | $12.35 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.48 | $0.00 | $13.48 |
| LABORER: COMMON OR GENERAL | $12.17 | $0.00 | $12.17 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $12.35 | $0.00 | $12.35 |
| LABORER GRADE CHECKER | $15.89 | $0.00 | $15.89 |
| IRONWORKER, REINFORCING | $17.05 | $0.00 | $17.05 |
| HIGHWAY/PARKING LOT STRIPING: OPERATOR (STRIPING MACHINE) | $20.12 | $0.00 | $20.12 |
| ELECTRICIAN | $20.41 | $7.49 | $27.90 |
| CEMENT MASON/CONCRETE FINISHER | $15.50 | $0.00 | $15.50 |
| CARPENTER (FORM WORK ONLY) | $15.25 | $0.00 | $15.25 |
Residential AL20260024 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER | $10.08 | $0.00 | $10.08 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $10.47 | $0.00 | $10.47 |
| ROOFER, INCLUDES SHAKE & SHINGLE, AND SINGLE PLY ROOFS | $7.50 | $0.00 | $7.50 |
| PLUMBER | $10.21 | $0.00 | $10.21 |
| PAINTER: BRUSH AND ROLLER, EXCLUDES DRYWALL FINISHING/TAPING | $9.79 | $0.00 | $9.79 |
| OPERATOR: BULLDOZER | $11.71 | $0.00 | $11.71 |
| OPERATOR: BACKHOE | $9.80 | $0.00 | $9.80 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $8.00 | $0.00 | $8.00 |
| LABORER: LANDSCAPE | $7.27 | $0.00 | $7.27 |
| LABORER: COMMON OR GENERAL | $7.50 | $0.00 | $7.50 |
| HVAC MECHANIC (INSTALLATION OF HVAC DUCT) | $10.83 | $0.00 | $10.83 |
| ELECTRICIAN | $10.73 | $0.00 | $10.73 |
| DRYWALL FINISHER/TAPER | $12.00 | $0.00 | $12.00 |
| CEMENT MASON/CONCRETE FINISHER | $8.46 | $0.00 | $8.46 |
| CARPENTER, INCLUDES DRYWALL HANGING | $12.07 | $0.00 | $12.07 |
| BRICKLAYER | $12.20 | $0.00 | $12.20 |
Get an email when rates change here
One watch per determination above; every email includes a stop link. Bidding a specific job? Pin it to your bid date instead.