Autauga County, Alabama: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Bidding a job in Autauga County? Pin your bid date to lock the revision that legally applies under the FAR ten-day rule, and get an email if anything moves before or after opening.
Building AL20260082 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $31.10 | $16.40 | $47.50 |
| BOILERMAKER | $34.21 | $23.92 | $58.13 |
| POWER EQUIPMENT OPERATOR: CRANE | $31.75 | $14.55 | $46.30 |
| IRONWORKER, STRUCTURAL | $33.75 | $14.03 | $47.78 |
| PIPEFITTER | $32.30 | $17.96 | $50.26 |
| PLUMBER | $35.20 | $13.51 | $48.71 |
| TRUCK DRIVER: DUMP TRUCK | $13.18 | $0.00 | $13.18 |
| TILE SETTER | $15.86 | $0.00 | $15.86 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $21.39 | $9.49 | $30.88 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT INSTALLATION | $16.16 | $0.00 | $16.16 |
| ROOFER | $12.06 | $0.00 | $12.06 |
| PAINTER: SPRAY | $14.31 | $0.00 | $14.31 |
| PAINTER (BRUSH AND ROLLER) | $15.41 | $0.00 | $15.41 |
| LABORER: PIPELAYER | $12.58 | $0.00 | $12.58 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $12.16 | $0.00 | $12.16 |
| LABORER: MASON TENDER - BRICK | $11.00 | $0.00 | $11.00 |
| LABORER: COMMON OR GENERAL | $12.29 | $0.00 | $12.29 |
| IRONWORKER, REINFORCING | $22.86 | $7.94 | $30.80 |
| ELECTRICIAN | $19.43 | $4.35 | $23.78 |
| CEMENT MASON/CONCRETE FINISHER | $17.16 | $0.73 | $17.89 |
| CARPENTER | $19.62 | $0.00 | $19.62 |
| BRICKLAYER | $19.81 | $0.00 | $19.81 |
OPERATOR 6 classifications · $14.69 to $20.69 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: ROLLER | $14.00 | $1.78 | $15.78 |
| OPERATOR: LOADER | $14.69 | $0.00 | $14.69 |
| OPERATOR: GRADER/BLADE | $17.52 | $0.89 | $18.41 |
| OPERATOR: FORKLIFT | $20.69 | $0.00 | $20.69 |
| OPERATOR: BULLDOZER | $16.37 | $0.00 | $16.37 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $16.69 | $0.00 | $16.69 |
Heavy AL20260115 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: DUMP TRUCK, INCLUDES WATER SEWER LINES | $12.56 | $2.12 | $14.68 |
| OPERATOR: LOADER, INCLUDES WATER SEWER LINES | $17.64 | $2.14 | $19.78 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE, INCLUDES WATER SEWER LINES | $14.84 | $0.00 | $14.84 |
| LABORER: PIPELAYER, INCLUDES WATER SEWER LINES | $11.95 | $0.00 | $11.95 |
| LABORER: COMMON OR GENERAL, INCLUDES WATER SEWER LINES | $12.33 | $0.00 | $12.33 |
| ELECTRICIAN | $19.56 | $0.00 | $19.56 |
| CEMENT MASON/CONCRETE FINISHER, INCLUDES WATER SEWER LINES | $13.78 | $0.00 | $13.78 |
| CARPENTER, INCLUDES FORM WORK | $18.72 | $7.91 | $26.63 |
Residential AL20260037 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER | $10.06 | $0.00 | $10.06 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $12.82 | $0.00 | $12.82 |
| ROOFER, INCLUDES BUILT UP, METAL, SHAKE & SHINGLE, AND SINGLE PLY ROOFS | $12.00 | $0.00 | $12.00 |
| PLUMBER | $10.95 | $0.00 | $10.95 |
| PAINTER | $8.00 | $0.00 | $8.00 |
| OPERATOR: LOADER (FRONT END) | $10.40 | $0.00 | $10.40 |
| OPERATOR: BULLDOZER | $12.60 | $0.00 | $12.60 |
| OPERATOR: BACKHOE | $11.45 | $0.00 | $11.45 |
| LABORER: PIPELAYER | $8.83 | $0.00 | $8.83 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $7.88 | $0.00 | $7.88 |
| LABORER: LANDSCAPE | $7.25 | $0.00 | $7.25 |
| LABORER: COMMON OR GENERAL | $7.30 | $0.00 | $7.30 |
| IRONWORKER, STRUCTURAL | $8.00 | $0.00 | $8.00 |
| IRONWORKER, ORNAMENTAL | $10.75 | $0.00 | $10.75 |
| HVAC MECHANIC (INSTALLATION OF HVAC DUCT) | $10.77 | $0.00 | $10.77 |
| ELECTRICIAN, INCLUDES INSTALLATION OF HVAC/TEMPERATURE CONTROLS | $11.23 | $0.00 | $11.23 |
| CEMENT MASON/CONCRETE FINISHER | $10.00 | $0.00 | $10.00 |
| CARPENTER, INCLUDES FORM WORK | $10.94 | $0.00 | $10.94 |
| BRICKLAYER | $14.79 | $0.00 | $14.79 |
Get an email when rates change here
One watch per determination above; every email includes a stop link. Bidding a specific job? Pin it to your bid date instead.